Schedule analysis

E8P02 Current project Beachline Expressway

Current schedule: E8P02 Update No. 20

Back Schedule Metrics

Improved Float and constraint totals now use the corrected activity scope and P6 fields.

Beachline Update#20 DD June 11 TD June 15

  • 534Not started activities
  • 95In progress activities
  • 583Completed activities
  • 97 Activities with zero or negative float
  • 42 Activities on longest path
  • 0 Activities with constraint
  • 6 Available Calendars
  • 18 Project Resources
  • 14 Project Milestones

Activity Types

  • 2Finish Milestones
  • 12Start Milestones
  • 1198Task Dependent

Project Dates

  • Schedule-level Dates: are computed from the activities in the selected XER and reflect that imported schedule state.
  • Project-level Dates: are stored on the P6 project record. They may be administrative or planned dates and do not necessarily move with activity updates.
  • Must Finish By Date: is a manually entered project deadline that may affect scheduling and is often left empty.
  • 17-Jun-17Last Save Date
  • 11-Jun-17Data Date
  • 20-Aug-18Must Finish By Date
  • 19-Aug-15Start Date (schedule-level)
  • 05-Sep-18Finish Date (schedule-level)
  • 1113 calendar daysProject Duration (schedule-level)
  • 19-Aug-15Start Date (project-level)
  • 05-Sep-18Finish Date (project-level)
  • 1113 calendar daysProject Duration (project-level)

Back Schedule Analysis

Now identified explicitly as P6 exported path data, not a recalculated network.

This table lists unfinished activities whose exported P6 driving_path_flag is set. It reflects the schedule state saved by P6 and is not an independent network recalculation. Confirm the schedule was recalculated before export.

Start Date, Finish Date, and Total Float provide context for the exported path designation.

Highlighted in red are activities with negative total float.

Activity IDActivity DescriptionStart DateFinish DateTotal Float
PH IIB - Base (Universal - JYP) - EB Outside Widening - LR - (STA 320 to 332)01-May-1714-Jun-17-11
PH IIB - Asphalt - Structural - EB Outside Widening (Univ to JYP) - STA 320 to 33214-Jun-1720-Jun-17-11
PH IIC - MOT Shift New Ramp Alignment - Ramp O20-Jun-1721-Jun-17-11
PH IIC - Remove Ramp O Diversion - Construct EB Roadway Tie-In21-Jun-1713-Jul-17-11
PH IIIA - Construct Diversion at Shingle Creek - WB Median Widening13-Jul-1703-Aug-17-11
PH IIIA - Construct Ramp Diversion P - Ramp P (Tie-in to SC Diversion)03-Aug-1710-Aug-17-11
PH IIIB - Demo Traffic Rails - WB Outside Widening Area (Bridge over Shingle Creek)10-Aug-1718-Aug-17-11
PH IIIB - Demo Bridge Deck - WB Outside Widening Area (Bridge over Shingle Creek)18-Aug-1728-Aug-17-11
PH IIIB - Remove Beams - WB Outside Widening Area (Bridge over Shingle Creek)28-Aug-1730-Aug-17-11
PH IIIB - Demo Pile Cap - WB Outside Widening Area (Bridge over Shingle Creek)30-Aug-1705-Sep-17-11
PH IIIB - Extract Pile - WB Outside Widening Area (Bridge over Shingle Creek)05-Sep-1708-Sep-17-11
PH IIIB - Production Pile (11-30)(Concrete) - WB Outside Widening Area (Bridge over Shingle Creek)08-Sep-1722-Sep-17-11
PH IIIB - Wall Bent 1 - WB Outside Widening Area (Bridge over Shingle Creek)22-Sep-1704-Oct-17-11
PH IIIB - End Bent 1 - WB Outside Widening Area (Bridge over Shingle Creek)04-Oct-1725-Oct-17-11
PH IIIB - Wall Bent 4 - WB Outside Widening Area (Bridge over Shingle Creek)25-Oct-1706-Nov-17-11
PH IIIB - End Bent 4 - WB Outside Widening Area (Bridge over Shingle Creek)06-Nov-1701-Dec-17-11
PH IIIB - Curing for End Bent 4 - WB Outside Widening Area (Bridge over Shingle Creek)01-Dec-1708-Dec-17-17
PH IIIB - Set Beams - WB Outside Widening Area (Bridge over Shingle Creek)08-Dec-1727-Dec-17-11
PH IIIB - Superstructure Deck SIP & Start Rebar - WB Outside Widening Area (Bridge over Shingle Creek)27-Dec-1726-Jan-18-11
PH IIIB - Superstructure Deck (Finish Rebar\Set Screed\Pour) - WB Outside Widening Area (Bridge over Shingle Creek)26-Jan-1816-Feb-18-11
PH IIIB - Approach Slabs - WB Outside Widening Area (Bridge over Shingle Creek)16-Feb-1805-Mar-18-11
PH IIIB - Lighting Conduit - WB Outside Widening Area (Bridge over Shingle Creek)06-Mar-1806-Mar-18-11
PH IIIB - Traffic Railing (32") - WB Outside Widening Area (Bridge over Shingle Creek)07-Mar-1809-Mar-18-11
PH IIIB - Grind and Groove - WB Outside Widening Area (Bridge over Shingle Creek)12-Mar-1815-Mar-18-11
PH MS - Start Phase IV Construction16-Mar-18-11
PH IV - Set Temp Traffic Barriers - EB Median Widening16-Mar-1821-Mar-18-11
PH IV - Demo Temporary - EB Median Widening22-Mar-1828-Mar-18-11
PH IV - Median Wall - Grading for Station 1 (I4 to International Drive)29-Mar-1830-Mar-18-11
PH IV - Median Wall - FFP Footing/Stem for Station 1 (I4 to International Drive)02-Apr-1813-Apr-18-11
PH IV - Median Wall - Construct/ slip Top for Station 1 (I4 to International Drive)16-Apr-1820-Apr-18-11
PH IV - Median Wall - Grading for Station 2 (International Drive to Universal)23-Apr-1830-Apr-18-11
PH IV - Median Wall - FFP Footing/Stem for Station 2 (International Drive to Universal)01-May-1821-May-18-11
PH IV - Median Wall - Construct/ slip Top for Station 2 (International Drive to Universal)22-May-1829-May-18-11
PH IV - Median Wall - Grading for Station 3 (Universal to JYP)30-May-1812-Jun-18-11
PH IV - Median Wall - FFP Footing/Stem for Station 3 (Universal to JYP)13-Jun-1826-Jun-18-11
PH IV - Median Wall - Construct/ slip Top for Station 3 (Universal to JYP)27-Jun-1805-Jul-18-11
PH IV - Grade for Station 3 (Universal to JYP) (B)06-Jul-1812-Jul-18-11
PH IV - Stabilization for Station 3 (Universal to JYP) (A)13-Jul-1818-Jul-18-11
PH IV - Base for Station 3 (Universal to JYP) (B)19-Jul-1831-Jul-18-11
PH IV - Asphalt - Structural - WB Median Widening01-Aug-1806-Aug-18-11
PH MS - Punch List/Acceptance07-Aug-1805-Sep-18-17
PH MS - Project Completion05-Sep-18-17

Now scoped to unfinished detail activities and separated from longest path status.

This table is a total-float filter, not a critical-path calculation. Zero or negative float identifies limited or negative schedule flexibility under the saved P6 dates and constraints. Use the On LP column to distinguish activities that P6 also marked on the exported longest path.

Activity IDActivity DescriptionOn LPTotal Float
PH MS - Project CompletionYes-17
PH MS - Substantial CompletionNo-5
PH IIIA - Construct Ramp Diversion P - Ramp P (Tie-in to SC Diversion)Yes-11
TEC Install and TestNo-4
PH PW - ITS Testing and Commissioning - Critical AreasNo0
PH MS - Start Phase IV ConstructionYes-11
PH MS - Punch List/AcceptanceYes-17
Precast ErectionNo-4
FRP Conc. Roof Dec/cNo-4
Const. Roof SystemNo-4
FRP Conc. Pad (Generator)No-4
Install Frames & DoorsNo-4
Const. Screen Wall (Con.)No-4
F+1 GeneratorNo-4
F+1 Fuel TankNo-4
Install Security SystemNo-4
Install Lightning ProtectionNo-4
Wall Treatments (Ply)No-4
Cont. LightningNo-1
Cont. HVACNo-4
Pull WireNo-4
Toll Facility Finishes and PunchlistNo-4
Toll Facility CONo-4
PH IIB - Asphalt - Structural - Ramp ONo-11
PH IIB - Base - Ramp ONo-11
PH IIB - Install ITS Poles (1-20)No0
PH IIB - Install ITS Poles (21-41)No0
PH IIB - Install CCTV's (1-8)No0
PH IIB - Install CCTV's (9-16)No0
PH IIB - Install CCTV's (17-22)No0
PH IIC - Remove Ramp O Diversion - Construct EB Roadway Tie-InYes-11
PH IIC - MOT Shift New Ramp Alignment - Ramp OYes-11
PH IV - Median Wall - Grading for Station 1 (I4 to International Drive)Yes-11
PH IV - Median Wall - FFP Footing/Stem for Station 1 (I4 to International Drive)Yes-11
PH IV - Median Wall - Construct/ slip Top for Station 1 (I4 to International Drive)Yes-11
PH IV - Median Wall - Grading for Station 2 (International Drive to Universal)Yes-11
PH IV - Median Wall - FFP Footing/Stem for Station 2 (International Drive to Universal)Yes-11
PH IV - Median Wall - Construct/ slip Top for Station 2 (International Drive to Universal)Yes-11
PH IV - Median Wall - Grading for Station 3 (Universal to JYP)Yes-11
PH IV - Median Wall - FFP Footing/Stem for Station 3 (Universal to JYP)Yes-11
PH IV - Median Wall - Construct/ slip Top for Station 3 (Universal to JYP)Yes-11
Fabricate and Deliver 042200 MasonryNo-4
Prepare and Submit 042200 MasonryNo-4
Review and Approve 042200 MasonryNo-4
PH IIIA - Construct Diversion at Shingle Creek - WB Median WideningYes-11
PH IIIB - Install Conduit/Boxes (JYP to TPK)No0
PH IIIB - Install ITS Cabinets/HardwareNo0
PH IV - Asphalt - Structural - EB Median WideningNo-10
PH IV - Demo Temporary - EB Median WideningYes-11
PH IV - Set Temp Traffic Barriers - EB Median WideningYes-11
PH IV - Temp Striping for Phase - EB Median WideningNo-5
PH IV - MOT Shift for Phase - EB Median WideningNo-5
PH IV - Asphalt - Overbuild & Friction - EB Outside WideningNo-5
PH IV - Pavement Markings (Final) - EB Outside WideningNo-5
PH IV - Asphalt - Structural - WB Median WideningYes-11
PH IV - Grade for Station 3 (Universal to JYP) (B)Yes-11
PH IV - Stabilization for Station 3 (Universal to JYP) (A)Yes-11
PH IV - Base for Station 3 (Universal to JYP) (B)Yes-11
PH IV - Grade for Station 3 (Universal to JYP) (A)No-10
PH IV - Stabilization for Station 3 (Universal to JYP) (A)No-10
PH IV - Base for Station 3 (Universal to JYP)No-10
PH IV - Set Temp Traffic Barriers - WB Median WideningNo-6
PH IV - Temp Striping for Phase - WB Median WideningNo-4
PH IV - MOT Shift for Phase - WB Median WideningNo-4
PH IV - Asphalt - Overbuild & Friction - WB Outside Widening AreaNo-4
PH IV - Pavement Markings (Final) - WB Outside Widening AreaNo-4
PH IIB - Asphalt - Structural - EB Outside Widening (Univ to JYP) - STA 320 to 332Yes-11
PH IIB - Base (Universal - JYP) - EB Outside Widening - LR - (STA 320 to 332)Yes-11
PH IIIB - Install Vehicle Detection Systems (1-11)No0
PH IIIB - Install Vehicle Detection Systems (12-22)No0
PH IIIB - Install Digital Message Signs (1-12)No0
PH IIIB - Install Digital Message Signs (13-23)No0
PH IIIB - Pull FOC (I-4 to International)No0
PH IIIB - Pull FOC ( International to Univ)No0
PH IIIB - Pull FOC (UNIV to JYP)No0
PH IIIB - Pull FOC (JYP to TPK)No0
PH IIIB - Splice/Terminate FOCNo0
PH IIIB - Production Pile (11-30)(Concrete) - WB Outside Widening Area (Bridge over Shingle Creek)Yes-11
PH IIIB - Install Conduit/Boxes (I-4 to International)No0
PH IIIB - Install Conduit/Boxes (Univ to JYP)No0
PH IIIB - Approach Slabs - WB Outside Widening Area (Bridge over Shingle Creek)Yes-11
PH IIIB - Lighting Conduit - WB Outside Widening Area (Bridge over Shingle Creek)Yes-11
PH IIIB - Traffic Railing (32") - WB Outside Widening Area (Bridge over Shingle Creek)Yes-11
PH IIIB - Grind and Groove - WB Outside Widening Area (Bridge over Shingle Creek)Yes-11
PH IIIB - Demo Traffic Rails - WB Outside Widening Area (Bridge over Shingle Creek)Yes-11
PH IIIB - Wall Bent 1 - WB Outside Widening Area (Bridge over Shingle Creek)Yes-11
PH IIIB - End Bent 1 - WB Outside Widening Area (Bridge over Shingle Creek)Yes-11
PH IIIB - Wall Bent 4 - WB Outside Widening Area (Bridge over Shingle Creek)Yes-11
PH IIIB - End Bent 4 - WB Outside Widening Area (Bridge over Shingle Creek)Yes-11
PH IIIB - Curing for End Bent 4 - WB Outside Widening Area (Bridge over Shingle Creek)Yes-17
PH IIIB - Set Beams - WB Outside Widening Area (Bridge over Shingle Creek)Yes-11
PH IIIB - Superstructure Deck SIP & Start Rebar - WB Outside Widening Area (Bridge over Shingle Creek)Yes-11
PH IIIB - Demo Bridge Deck - WB Outside Widening Area (Bridge over Shingle Creek)Yes-11
PH IIIB - Remove Beams - WB Outside Widening Area (Bridge over Shingle Creek)Yes-11
PH IIIB - Demo Pile Cap - WB Outside Widening Area (Bridge over Shingle Creek)Yes-11
PH IIIB - Extract Pile - WB Outside Widening Area (Bridge over Shingle Creek)Yes-11
PH IIIB - Superstructure Deck (Finish Rebar\Set Screed\Pour) - WB Outside Widening Area (Bridge over Shingle Creek)Yes-11

Different activity IDs can legitimately share a description, but repeated wording can make tracking, communication, resource review, and claim analysis less precise.

Review duplicates where the wording creates ambiguity. Add a phase, location, system, or another distinguishing qualifier when the activities represent different work.

TotalActivity DescriptionActivity IDs
2PH IV - Stabilization for Station 3 (Universal to JYP) (A)IVWBM-RW140, IVWBM-RW270

Out-of-sequence progress occurs when recorded work does not follow the current dependency order. A small amount can be normal; repeated findings may indicate changed field sequencing, incomplete progress updates, or logic that no longer reflects the work plan.

Review the cause and project context for each material finding. Revise logic or update procedures only when the supporting record shows that a change is appropriate.

Activity IDActivity DescriptionOn LPAct start dateParent end date
PH MS - NTP2 - Start Construction (35 days from NTP 1= Contract date )Yes20-Sep-1511-Jun-17
PH MS - Construction MobilizationYes19-Aug-1511-Jun-17
PH MS - Start Phase IA ConstructionYes20-Sep-1511-Jun-17
PH MS - Start Phase IB ConstructionYes20-Nov-1511-Jun-17
PH MS - Start Phase IIA ConstructionNo19-Sep-1611-Jun-17
PH MS - Start Phase IIB ConstructionNo04-Oct-1611-Jun-17
PH IA - Overbuild Shoulder - EB Outside Widening (SR528)Yes20-Sep-1511-Jun-17
PH IA - Set Erosion Control Devices - EB Outside WideningYes21-Sep-1511-Jun-17
PH IA - Clear & Grub - EB Outside WideningNo22-Sep-1511-Jun-17
PH IA - Drill Scuppers in Bridge (Shingle Creek) - EB Outside WideningYes08-Oct-1511-Jun-17
PH IA - Clear & Grub - EB Outside Widening (I-4 to Ramp H)No22-Feb-1611-Jun-17
PH IA - Jack & Bore 42" (Sta 351+00 near Duke energy access platform) - EB Outside Widening (SR528)No06-Jul-1611-Jun-17
PH IA - Drainage (42") @ JYP Interchange - EB Outside Widening (SR528)No25-Jul-1611-Jun-17
PH IA - Install Advance Sign & Traffic Control Devices - EB Outside WideningYes28-Sep-1511-Jun-17
PH IA - Temp Striping for Phase IB - EB Outside Widening (SR528)Yes27-Sep-1511-Jun-17
PH IA - Noise/Sound Wall Prep Work (W-1) - EB Outside WideningNo04-Jan-1611-Jun-17
PH IA - Install Posts (1-101)- EB Outside WideningNo29-Apr-1611-Jun-17
PH IA - Install Posts (102- 203) - EB Outside WideningNo09-May-1611-Jun-17
PH IA - Noise/Sound Wall Prep Work (W-2) - EB Outside WideningNo22-Feb-1611-Jun-17
PH IA - Install Posts (204-305) - EB Outside WideningNo18-May-1611-Jun-17
PH IA - Install Posts (306- 409) - EB Outside WideningNo26-May-1611-Jun-17
PH IA - Install Panels (0-32000 SF) - EB Outside WideningNo27-Jun-1611-Jun-17
PH IA - Install Panels (32000-64000 SF) - EB Outside WideningNo29-Jun-1611-Jun-17
PH IA - Install Panels (64000-96000 SF)- EB Outside WideningNo05-Jul-1611-Jun-17
PH IA - Install Panels (96000-128000 SF)- EB Outside WideningNo08-Jul-1611-Jun-17
PH IA - Install Panels (128000-160000 SF) - EB Outside WideningNo12-Jul-1611-Jun-17
PH IA - Set Temp Traffic Barriers - Interchanges Roads International DrNo21-Oct-1511-Jun-17
PH IA - Set Temp Traffic Barriers - Interchanges Roads Universal AvnNo09-Nov-1511-Jun-17
PH IA - Set Temp Traffic Barriers - Interchanges Roads John Young PKWNo17-Nov-1511-Jun-17
PH IA - Mill & Resurface Transition (Ramp A)Yes25-Oct-1511-Jun-17
PH IA - Over Build Shoulder- Ramp AYes26-Oct-1511-Jun-17
PH IA - Over Build Shoulder - Ramp DYes20-Sep-1511-Jun-17
PH IA - Guardrail Replacement (Ramp A)Yes25-Oct-1511-Jun-17
PH IA - Close and Detour (Ramp A)Yes25-Oct-1511-Jun-17
PH IA - Set Temp Traffic Barriers - Ramp AYes26-Oct-1511-Jun-17
PH IA - Set Temp Traffic Barriers for Phase IB - WB Median WideningNo01-Nov-1511-Jun-17
PH IA - Set Temp Traffic Barriers for Phase IB - EB Median WideningNo29-Oct-1511-Jun-17
PH IA - Overbuild Shoulder - WB Outside Widening Area (SR528)Yes23-Sep-1511-Jun-17
PH IA - Pond EXCAVATION (Shape 4A & 5A) - WB Outside Widening AreaNo26-Oct-1511-Jun-17
PH IA - Embankment(Duke energy access platform & Poles) - WB Outside Widening AreaNo05-Oct-1511-Jun-17
PH IA - Set Erosion Control Devices - WB Outside Widening AreaYes21-Sep-1511-Jun-17
PH IA - Clear & Grub - WB Outside Widening AreaNo22-Sep-1511-Jun-17
PH IA - Drill Scuppers in Bridge (Shingle Creek) - WB Outside Widening AreaYes13-Oct-1511-Jun-17
PH IA - Drainage (42") @ JYP Interchange - WB Outside Widening Area (SR528)No10-Nov-1611-Jun-17
PH IA - Install Advance Sign & Traffic Control Devices - WB Outside Widening AreaYes20-Sep-1511-Jun-17
PH IA - Temp Striping for Phase IB - WB Outside Widening Area (SR528)Yes28-Sep-1511-Jun-17
PH IB - Asphalt - Structural - EB Median Widening (I-4 to I-Drive)No02-Mar-1711-Jun-17
PH IB - Asphalt - Structural - EB Median Widening (I-Drive to Univ)No06-Feb-1711-Jun-17
PH IB - Asphalt - Structural - EB Median Widening (Univ to JYP)Yes23-Jan-1711-Jun-17
PH IB - Median Clearing and Grubbing - EB Median WideningNo26-Oct-1511-Jun-17
PH IB - Grade for Permanent Shoulder Construction (JYP-TRP) - EB Median WideningNo11-Jul-1611-Jun-17
PH IB - Stabilization for Permanent Shoulder Construction (JYP-TRP) - EB Median WideningNo13-Jul-1611-Jun-17
PH IB - Grade (I4-International Drive) - EB Median WideningNo06-Feb-1711-Jun-17
PH IB - Grade (International Drive - Universal) - EB Median WideningNo30-Jan-1711-Jun-17
PH IB - Grade (Universal - JYP) - EB Median WideningYes19-Dec-1611-Jun-17
PH IB - Stabilization (I4-international Drive) - EB Median WideningNo17-Feb-1711-Jun-17
PH IB - Stabilization (International Drive - Universal) - EB Median WideningNo08-Feb-1711-Jun-17
PH IB - Stabilization (Universal - JYP) - EB Median WideningYes18-Jan-1711-Jun-17
PH IB - Base (I4-International Drive) - EB Median WideningNo13-Jul-1611-Jun-17
PH IB - Base (International Drive - Universal) - EB Median WideningNo08-Feb-1711-Jun-17
PH IB - Base (Universal - JYP) - EB Median WideningYes18-Jan-1711-Jun-17
PH IB - Guard Rail Removal - EB Median WideningYes10-Dec-1511-Jun-17
PH IB - Base for Permanent Shoulder Construction (JYP-TRP) - EB Median WideningNo01-Nov-1616-Jun-17
PH IB - Pavement for Permanent Shoulder Construction (JYP-TRP) - EB Median WideningNo17-Nov-1622-Jun-17
PH IB - Construct Crane Access - EB Median Widening (Bridge over Shingle Creek)No05-Nov-1511-Jun-17
PH IB - DemoTraffic Rail / End Bents - EB Median Widening (Bridge over Shingle Creek)No22-Nov-1511-Jun-17
PH IB - Construct Crane Access - EB Median Widening (Bridge over John Young PKWY)No04-Dec-1511-Jun-17
PH IB - Demo Traffic Rails - EB Median Widening (Bridge over John Young PKWY)No04-Jan-1611-Jun-17
PH IB - Construct Crane Access - EB Median Widening (Bridge over International DR)No17-Mar-1611-Jun-17
PH IB - Demo Traffic Rails - EB Median Widening (Bridge over International DR)No14-Mar-1611-Jun-17
PH IB - Test Pile (Concrete) - EB Median Widening (Bridge over Shingle Creek)No20-Nov-1511-Jun-17
PH IB - Production Pile (Concrete) - EB Median Widening (Bridge over Shingle Creek)No18-Jan-1611-Jun-17
PH IB - Temp Sheet Pile - EB Median Widening (Bridge over International DR)No16-May-1611-Jun-17
PH IB - Temp Sheet Pile - EB Median Widening (Bridge over John Young PKWY)No06-Mar-1611-Jun-17
PH IB - Drive Production Pile (H Piles) - EB Median Widening (Bridge over John Young PKWY)No25-Jan-1611-Jun-17
PH IB - Production Pile - EB Median Widening (Bridge over International DR)No28-Mar-1611-Jun-17
PH IB - Construct Crane Access - EB Median Widening (Bridge over universal BLVD)No21-Feb-1611-Jun-17
PH IB - Pier 2, (F/R/P)(Footer, Column & Pier Cap) - EB Median Widening (Bridge over International DR)No18-May-1611-Jun-17
PH IB - Demo Traffic Rails - EB Median Widening (Bridge over universal BLVD)No29-Feb-1611-Jun-17
PH IB - Test Pile - EB Median Widening (Bridge over universal BLVD)No10-Mar-1611-Jun-17
PH IB - Temp Sheet Pile - EB Median Widening (Bridge over universal BLVD)No08-Jun-1611-Jun-17
PH IB - Production Pile - EB Median Widening (Bridge over universal BLVD)No10-Mar-1611-Jun-17
PH IB - Curing for Pier 2, (Footer, Column & Pier Cap) - EB Median Widening (Bridge over International DR)No27-Jul-1611-Jun-17
PH IB - Removal of Concrete Forms for Pier 2, (Footer, Column & Pier Cap) - WB Median Widening (Bridge over InternationNo04-Aug-1611-Jun-17
PH IB - Temp Sheet Pile Removal - EB Median Widening (Bridge over International DR)No25-Jul-1611-Jun-17
PH IB - Wall Bent 1 - EB Median Widening (Bridge over International DR)No18-Apr-1611-Jun-17
PH IB - Rip Rap Under Bridge - EB Median Widening (Bridge over Shingle Creek)No16-Feb-1611-Jun-17
PH IB - Pier 2 & 3 (F/R/P)( Pile Cap) - EB Median Widening (Bridge over Shingle Creek)No29-Jan-1611-Jun-17
PH IB - Pier 2, 3, 4(F/R/P) ( Pier Cap) - EB Median Widening (Bridge over John Young PKWY)No06-May-1611-Jun-17
PH IB - End Bent 1 - EB Median Widening (Bridge over International DR)No18-Apr-1611-Jun-17
PH IB - Wall Bent 3 - EB Median Widening (Bridge over International DR)No09-May-1611-Jun-17
PH IB - Curing for Pier 2, 3, (Pile Cap) - EB Median Widening (Bridge over Shingle Creek)No24-Feb-1611-Jun-17
PH IB - Remove Concrete Form for Pier 2, 3, (Pile Cap) - EB Median Widening (Bridge over Shingle Creek)No02-Mar-1611-Jun-17
PH IB - End Bent 3 - EB Median Widening (Bridge over International DR)No09-May-1611-Jun-17
PH IB - Curing for End Bent 3 - EB Median Widening (Bridge over International DR)No12-May-1611-Jun-17
PH IB - End Bent 1 - EB Median Widening (Bridge over Shingle Creek)No28-Apr-1611-Jun-17
PH IB - Curing For Pier 2, 3, 4(Footer, Column & Pier Cap) - EB Median Widening (Bridge over John Young PKWY)No02-Aug-1611-Jun-17
PH IB - Set Beams - EB Median Widening (Bridge over International Drive)No13-Oct-1611-Jun-17
PH IB - Superstructure Deck - EB Median Widening (Bridge over International Drive)No24-Oct-1611-Jun-17
PH IB - Remove Concrete Forms for Pier 2, 3, 4 (Footer, Column & Pier Cap) - EB Median Widening (Bridge over John YoungNo26-Apr-1611-Jun-17
PH IB - Temp Sheet Pile Removal - EB Median Widening (Bridge over John Young PKWY)No05-May-1611-Jun-17
PH IB - Wall Bent 1 - EB Median Widening (Bridge over John Young PKWY)No05-Aug-1611-Jun-17
PH IB - End Bent 1 - EB Median Widening (Bridge over John Young PKWY)No03-Aug-1611-Jun-17
PH IB - Wall Bent 5 - EB Median Widening (Bridge over John Young PKWY)No13-Jun-1611-Jun-17
PH IB - End Bent 4 - EB Median Widening (Bridge over Shingle Creek)No05-May-1611-Jun-17
PH IB - Pier 2,(F/R/P) (Footer, Column & Pier Cap) - EB Median Widening (Bridge over Universal BLVD)No10-Jun-1611-Jun-17
PH IB - Approach Slabs - EB Median Widening (Bridge over International DR)No12-Jan-1711-Jun-17
PH IB - Concrete Slope Pavement - EB Median Widening (Bridge over International DR)No13-Jun-1611-Jun-17
PH IB - End Bent 5 - EB Median Widening (Bridge over John Young PKWY)No13-Jun-1611-Jun-17
PH IB - Lighting Conduit - EB Median Widening (Bridge over International DR)No26-Jan-1711-Jun-17
PH IB - Traffic Railing (32") - EB Median Widening (Bridge over International DR)No07-Feb-1711-Jun-17
PH IB - Grind and Groove - EB Median Widening (Bridge over International DR)No20-Feb-1711-Jun-17
PH IB - Curing for Pier 2,(Footer, Column & Pier Cap) - EB Median Widening (Bridge over Universal BLVD)No04-Aug-1611-Jun-17
PH IB - Set Beams - EB Median Widening (Bridge over Shingle Creek)No23-May-1611-Jun-17
PH IB - Removal concrete form for Pier 2,(Footer, Column & Pier Cap) - EB Median Widening (Bridge over Universal BLVD)No05-Aug-1611-Jun-17
PH IB - Temp Sheet Pile Removal - EB Median Widening (Bridge over universal BLVD)No26-Jul-1611-Jun-17
PH IB - Wall Bent 1 - EB Median Widening (Bridge over universal BLVD)No02-Sep-1611-Jun-17
PH IB - Set Beams - EB Median Widening (Bridge over John Young PKWY)No27-Sep-1611-Jun-17
PH IB - Superstructure Deck - EB Median Widening (Bridge over John Young PKWY)No21-Oct-1611-Jun-17
PH IB - End Bent 1 - EB Median Widening (Bridge over universal BLVD)No18-Aug-1611-Jun-17
PH IB - Superstructure Deck- EB Median Widening (Bridge over Shingle Creek)No26-May-1611-Jun-17
PH IB - Wall Bent 3 - EB Median Widening (Bridge over universal BLVD)No06-May-1611-Jun-17
PH IB - End Bent 3 - EB Median Widening (Bridge over universal BLVD)No20-Apr-1611-Jun-17
PH IB - Curing for End Bent 5 - EB Median Widening (Bridge over John Young PKWY)No22-Jul-1611-Jun-17
PH IB - Approach Slabs - EB Median Widening (Bridge over John Young PKWY)No15-Feb-1711-Jun-17
PH IB - Concrete Slope Pavement - EB Median Widening (Bridge over John Young PKWY)No12-Sep-1611-Jun-17
PH IB - Set Beams - EB Median Widening (Bridge over Universal BLVD)No11-Oct-1611-Jun-17
PH IB - Superstructure Deck - EB Median Widening Bridge over Universal BLVD)No24-Oct-1611-Jun-17
PH IB - Lighting Conduit - EB Median Widening (Bridge over John Young PKWY)No01-Feb-1711-Jun-17
PH IB - Traffic Railing (32") - EB Median Widening (Bridge over John Young PKWY)No03-Mar-1711-Jun-17
PH IB - Grind and Groove - EB Median Widening (Bridge over John Young PKWY)No28-Feb-1711-Jun-17
PH IB - Approach Slabs - EB Median Widening (Bridge over Shingle Creek)No13-Jul-1611-Jun-17
PH IB - Grind and Groove - EB Median Widening (Bridge over Shingle Creek)No03-Aug-1611-Jun-17
PH IB - Approach Slabs - EB Median Widening (Bridge over universal BLVD)No20-Jan-1711-Jun-17
PH IB - Concrete Slope Pavement - EB Median Widening (Bridge over universal BLVD)No06-Jun-1611-Jun-17
PH IB - Lighting Conduit - EB Median Widening (Bridge over universal BLVD)No30-Jan-1711-Jun-17
PH IB - Traffic Railing (32") - EB Median Widening (Bridge over universal BLVD)No09-Feb-1711-Jun-17
PH IB - Grind and Groove - EB Median Widening (Bridge over universal BLVD)No21-Feb-1711-Jun-17
PH IB - Demo Bridge Deck - EB Median Widening (Bridge over International DR)No14-Mar-1611-Jun-17
PH IB - Demo Bridge Deck - EB Median Widening (Bridge over universal BLVD)No29-Feb-1611-Jun-17
PH IB - Demo Bridge Deck - EB Median Widening (Bridge over Shingle Creek)No22-Nov-1511-Jun-17
PH IB - Remove Beams - EB Median Widening (Bridge over Shingle Creek)No09-Dec-1511-Jun-17
PH IB - Demo Pile Caps - EB Median Widening (Bridge over Shingle Creek)No20-Dec-1511-Jun-17
PH IB - Extract Piles - EB Median Widening (Bridge over Shingle Creek)No30-Jan-1611-Jun-17
PH IB - Demo Bridge Deck - EB Median Widening (Bridge over John Young PKWY)No04-Jan-1611-Jun-17
PH IB - Pier 2, 3, 4(F/R/P) (Footer, Column) - EB Median Widening (Bridge over John Young PKWY)No09-Mar-1611-Jun-17
PH IB - Curing for End Bent 3 - EB Median Widening (Bridge over universal BLVD)No10-May-1611-Jun-17
PH IB - Curing for End Bent 4 - EB Median Widening (Bridge over Shingle Creek)No18-May-1611-Jun-17
PH IB - Bolt/Pin Temp B/W - EB Median Widening (Bridge over Shingle Creek)No04-Aug-1611-Jun-17
PH IB - Set Temp Traffic Barriers for Phase IIA - EB Median WideningNo18-Jul-1611-Jun-17
PH IB - Temp Striping for Phase IIA - EB Median WideningNo18-Jul-1611-Jun-17
PH IB - Construct Diversion at Shingle Creek- EB Median WideningNo20-Jun-1611-Jun-17
PH IB - Median Wall - Grading (JYP to TPK)No11-May-1611-Jun-17
PH IB - Median Wall - FFP Footing/Stem (JYP to TPK)No20-May-1611-Jun-17
PH IB - Wire (mse) Retaining Wall TW 18 - EB Median Widening (SR528)No06-Jun-1611-Jun-17
PH IB - Wire (mse) Retaining Wall TW 20 - EB Median Widening (SR528)No06-Jun-1611-Jun-17
PH IB - Pond Excav/Embank JYP to TPK - EB Outside WideningNo16-Nov-1511-Jun-17
PH IB - Pond Excav/Embank I-4 to Int. Dr. - EB Outside WideningNo16-Jan-1711-Jun-17
PH IB - Pond Excav/Embank JYP to Universal - WB Outside WideningNo16-Nov-1511-Jun-17
PH IB - Pond Excav/Embank Universal to Int. Dr. - WB Outside WideningNo19-Nov-1513-Jun-17
PH IB - Pond Excav/Embank Universal to Int. Dr. - EB Outside WideningNo16-Nov-1511-Jun-17
PH IB - Pond Excav/Embank Universal to JYP - EB Outside WideningNo30-Nov-1513-Jun-17
PH IB - Pond Excav/Embank Int. Dr. to I-4 - WB Outside WideningNo18-Jan-1616-Jun-17
PH IB - Remove Existing Overhead Sign (sta 356+25) & Foundation - EB Outside WideningNo08-Sep-1611-Jun-17
PH IB - Drainage (Pond 5C @ John Young) - EB Outside Widening (Ponds)No04-Aug-1619-Jun-17
PH IB - Asphalt - Structural - Ramp C (Redundant)No19-Dec-1611-Jun-17
PH IB - Embankment - Ramp C (Redundant)No19-Dec-1611-Jun-17
PH IB - Guardrail (Roadway) - Ramp B/C Gore (Activity Not Req'd)No19-Dec-1606-Jul-17
PH IB - Clear & Grub/Demo - Ramp C (Redundant)No19-Dec-1611-Jun-17
PH IB - Performance Turf, SOD - Ramp C (Redundant)No19-Dec-1611-Jun-17
PH IB - Guardrail (Roadway) - Ramp C (Redundant)No19-Dec-1611-Jun-17
PH IB - Install Drilled Shafts (1-13)No04-Mar-1611-Jun-17
PH IB - Install High Mast/Service (1-3)No06-Jun-1611-Jun-17
PH IB - Stabilization - Ramp C (Redundant)No19-Dec-1611-Jun-17
PH IB - Base - Ramp C (Redundant)No19-Dec-1611-Jun-17
PH IB - Set Temp Traffic Barriers - Ramp B/C GoreNo22-May-1711-Jun-17
PH IB - Set Temp Traffic Barriers - Ramp C (Redundant)No19-Dec-1611-Jun-17
PH IB - Asphalt - Structural - WB Median WideningNo16-Nov-1611-Jun-17
PH IB - Median Clearing and Grubbing - WB Median WideningNo27-Oct-1511-Jun-17
PH IB - Grade for Permanent Shoulder Construction (JYP-TRP) - WB Median WideningNo06-Jun-1611-Jun-17
PH IB - Stabilization for Permanent Shoulder Construction (JYP-TRP) - WB Median WideningNo13-Jul-1611-Jun-17
PH IB - Grade (JYP-Universal) - WB Median WideningNo26-Oct-1611-Jun-17
PH IB - Stabilization (JYP-Universal) - WB Median WideningNo28-Oct-1611-Jun-17
PH IB - Base (JYP-Universal) - WB Median WideningNo03-Nov-1611-Jun-17
PH IB - Grade (Universal-International Drv.) - WB Median WideningNo14-Dec-1611-Jun-17
PH IB - Stabilization (Universal-International Drv.) - WB Median WideningNo14-Dec-1611-Jun-17
PH IB - Base (Universal-International Drv.) - WB Median WideningNo14-Dec-1611-Jun-17
PH IB - Grade (International Drive-I4) - WB Median WideningNo15-Dec-1611-Jun-17
PH IB - Stabilization (International Drv.-I4) - WB Median WideningNo15-Dec-1611-Jun-17
PH IB - Base (International Drv.-I4) - WB Median WideningNo15-Dec-1611-Jun-17
PH IB - Base for Permanent Shoulder Construction (JYP-TRP) - WB Median WideningNo27-Oct-1616-Jun-17
PH IB - Pavement for Permanent Shoulder Construction (JYP-TRP) - WB Median WideningNo15-Nov-1622-Jun-17
PH IB - Pavement for Permanent Shoulder Construction (Universal-International Drv.) - WB Median WideningNo18-Jul-1611-Jun-17
PH IB - Drainage for JYP Interchange (Sta 354 +04)No12-Apr-1611-Jun-17
PH IB - Drainage for JYP to STA 390No18-Feb-1611-Jun-17
PH IB - Drainage for JYP to Int. Dr. (Sta 354+04 to 234+50)No12-Apr-1611-Jun-17
PH IB - Drainage for STA 390 to TPKNo08-Feb-1611-Jun-17
PH IB - Construct Crane Access - WB Median Widening (Bridge over International DR)No17-Mar-1611-Jun-17
PH IB - Demo Traffic Rail - WB Median Widening (Bridge over International DR)No14-Mar-1611-Jun-17
PH IB - Test Pile H-Piles - WB Median Widening (Bridge over International DR)No28-Mar-1611-Jun-17
PH IB - Temp Sheet Pile - WB Median Widening (Bridge over International DR)No16-May-1611-Jun-17
PH IB - Production Pile - WB Median Widening (Bridge over International DR)No28-Mar-1611-Jun-17
PH IB - Construct Crane Access - WB Median Widening (Bridge over universal BLVD)No21-Feb-1611-Jun-17
PH IB - Pier 2, (F/R/P)(Footer, Column & Pier Cap) - WB Median Widening (Bridge over International DR)No18-May-1611-Jun-17
PH IB - Demo Traffic Rail / End Bents - WB Median Widening (Bridge over universal BLVD)No29-Feb-1611-Jun-17
PH IB - Test Pile Concrete - WB Median Widening (Bridge over universal BLVD)No10-Aug-1611-Jun-17
PH IB - Temp Sheet Pile - WB Median Widening (Bridge over universal BLVD)No08-Jun-1611-Jun-17
PH IB - Production Pile Concrete - WB Median Widening (Bridge over universal BLVD)No10-Mar-1611-Jun-17
PH IB - Curing for Pier 2, (Footer, Column & Pier Cap) - WB Median Widening (Bridge over International DR)No27-Jul-1611-Jun-17
PH IB - Construct Crane Access - WB Median Widening (Bridge over John Young PKWY)No04-Dec-1511-Jun-17
PH IB - Demo Traffic Rails - WB Median Widening (Bridge over John Young PKWY)No04-Jan-1611-Jun-17
PH IB - Test Pile (H Piles) - WB Median Widening (Bridge over John Young PKWY)No14-Dec-1511-Jun-17
PH IB - Removal of Concrete Forms for Pier 2, (Footer, Column & Pier Cap) - (Bridge over International DR)No04-Aug-1611-Jun-17
PH IB - Temp Sheet Pile Removal - WB Median Widening (Bridge over International DR)No25-Jul-1611-Jun-17
PH IB - Wall Bent 1 - WB Median Widening (Bridge over International DR)No18-Apr-1611-Jun-17
PH IB - End Bent 1 - WB Median Widening (Bridge over International DR)No18-Apr-1611-Jun-17
PH IB - Temp Sheet Pile - WB Median Widening (Bridge over John Young PKWY)No06-Mar-1611-Jun-17
PH IB - Production Pile (H Piles) - WB Median Widening (Bridge over John Young PKWY)No25-Jan-1611-Jun-17
PH IB - Wall Bent 3 - WB Median Widening (Bridge over International DR)No09-May-1611-Jun-17
PH IB - End Bent 3 - WB Median Widening (Bridge over International DR)No05-May-1611-Jun-17
PH IB - Pier 2, 3, 4(F/R/P) (Footer, Column & Pier Cap) - WB Median Widening (Bridge over John Young PKWY)No09-Mar-1611-Jun-17
PH IB - Set Beams - WB Median Widening (Bridge over International Drive)No13-Oct-1611-Jun-17
PH IB - Superstructure Deck - WB Median Widening (Bridge over International Drive)No24-Oct-1611-Jun-17
PH IB - Curing For Pier 2, 3, 4(Footer, Column & Pier Cap) - WB Median Widening (Bridge over John Young PKWY)No02-Aug-1611-Jun-17
PH IB - Pier 2, (F/R/P)(Footer, Column & Pier Cap) - WB Median Widening (Bridge over Universal BLVD)No13-Jun-1611-Jun-17
PH IB - Approach Slabs - WB Median Widening (Bridge over International DR)No12-Jan-1711-Jun-17
PH IB - Concrete Slope Pavement - WB Median Widening (Bridge over International DR)No13-Jun-1611-Jun-17
PH IB - Removal of Concrete forms for Pier 2, 3, 4 (Footer, Column & Pier Cap) - WB Median Widening (Bridge over JYP)No09-Aug-1611-Jun-17
PH IB - Wall Bent 1 - WB Median Widening (Bridge over John Young PKWY)No05-Aug-1611-Jun-17
PH IB - Lighting Conduit - WB Median Widening (Bridge over International DR)No26-Jan-1711-Jun-17
PH IB - Traffic Railing (32") - WB Median Widening (Bridge over International DR)No07-Feb-1711-Jun-17
PH IB - Temp Sheet Pile Removal - WB Median Widening (Bridge over John Young PKWY)No05-May-1611-Jun-17
PH IB - End Bent 1 - WB Median Widening (Bridge over John Young PKWY)No03-Aug-1611-Jun-17
PH IB - Grind and Groove - WB Median Widening (Bridge over International DR)No20-Feb-1711-Jun-17
PH IB - Curing for Pier 2, (Footer, Column & Pier Cap) - WB Median Widening (Bridge over Universal BLVD)No04-Aug-1611-Jun-17
PH IB - Wall Bent 5 - WB Median Widening (Bridge over John Young PKWY)No13-Jun-1611-Jun-17
PH IB - Removal of Concrete Forms for Pier 2, (Footer, Column & Pier Cap) - WB Median Widening (Bridge over Universal BLNo05-Aug-1611-Jun-17
PH IB - Temp Sheet Pile Removal - WB Median Widening (Bridge over universal BLVD)No26-Jul-1611-Jun-17
PH IB - Wall Bent 1 - WB Median Widening (Bridge over universal BLVD)No02-Sep-1611-Jun-17
PH IB - End Bent 5 - WB Median Widening (Bridge over John Young PKWY)No13-Jun-1611-Jun-17
PH IB - End Bent 1 - WB Median Widening (Bridge over universal BLVD)No18-Aug-1611-Jun-17
PH IB - Wall Bent 3 - WB Median Widening (Bridge over universal BLVD)No06-May-1611-Jun-17
PH IB - Set Beams - WB Median Widening (Bridge over John Young PKWY)No27-Sep-1611-Jun-17
PH IB - End Bent 3 - WB Median Widening (Bridge over universal BLVD)No20-Apr-1611-Jun-17
PH IB - Superstructure Deck - WB Median Widening (Bridge over John Young PKWY)No18-Nov-1611-Jun-17
PH IB - Set Beams - WB Median Widening (Bridge over Universal BLVD)No11-Oct-1611-Jun-17
PH IB - Superstructure Deck - WB Median Widening Bridge over Universal BLVD)No06-Dec-1611-Jun-17
PH IB - Approach Slabs - WB Median Widening (Bridge over John Young PKWY)No15-Feb-1711-Jun-17
PH IB - Concrete Slope Pavement - WB Median Widening (Bridge over John Young PKWY)No06-Sep-1611-Jun-17
PH IB - Lighting Conduit - WB Median Widening (Bridge over John Young PKWY)No31-Jan-1711-Jun-17
PH IB - Traffic Railing (32") - WB Median Widening (Bridge over John Young PKWY)No06-Mar-1711-Jun-17
PH IB - Approach Slabs - WB Median Widening (Bridge over universal BLVD)No25-Jan-1711-Jun-17
PH IB - Concrete Slope Pavement - WB Median Widening (Bridge over universal BLVD)No15-Sep-1611-Jun-17
PH IB - Grind and Groove - WB Median Widening (Bridge over John Young PKWY)No27-Feb-1711-Jun-17
PH IB - Lighting Conduit - WB Median Widening (Bridge over universal BLVD)No31-Jan-1711-Jun-17
PH IB - Traffic Railing (32") - WB Median Widening (Bridge over universal BLVD)No09-Feb-1711-Jun-17
PH IB - Grind and Groove - WB Median Widening (Bridge over universal BLVD)No21-Feb-1711-Jun-17
PH IB - Demo Bridge Deck- WB Median Widening (Bridge over universal BLVD)No22-Mar-1611-Jun-17
PH IB - Demo Bridge Deck - WB Median Widening (Bridge over John Young PKWY)No04-Jan-1611-Jun-17
PH IB - Demo Bridge Deck - WB Median Widening (Bridge over International DR)No14-Mar-1611-Jun-17
PH IB - Curing for End Bent 5 - WB Median Widening (Bridge over John Young PKWY)No22-Jul-1611-Jun-17
PH IB - Curing for End Bent 3 - WB Median Widening (Bridge over International DR)No13-May-1611-Jun-17
PH IB - Curing for End Bent 3 - WB Median Widening (Bridge over universal BLVD)No16-May-1611-Jun-17
PH IB - Construct Diversion at I-Drive - WB Median WideningNo08-Feb-1711-Jun-17
PH IB - Median Wall - Construct/ slip Top (JYP to TPK)No27-Jun-1611-Jun-17
PH IB - Wire (mse) Retaining Wall TW 19 - WB Median Widening (SR528)No06-Jun-1611-Jun-17
PH IB - Wire (mse) Retaining Wall TW 21 - WB Median Widening (SR528)No06-Jun-1611-Jun-17
PH IB - Pond Excav/Embank JYP to TPK - WB Outside WideningNo07-Dec-1516-Jun-17
PH IB - Jack & Bore JYP Interchange (Sta 354 +04)No11-Apr-1611-Jun-17
PH IB - Jack & Bore JYP to TPK (East of Sta 354+04 to 415+33)No06-Jan-1611-Jun-17
PH IB - Jack & Bore JYP to Int. Dr. (Sta 354+04 to 234+50)No17-Mar-1611-Jun-17
PH IB - Drainage Outfalls (Pond 4A @ John Young) - WB Outside Widening Area (Ponds)No13-Jul-1611-Jun-17
PH IB - Drainage Outfalls (Pond 5A @ John Young) - WB Outside Widening Area (Ponds)No24-Oct-1606-Jul-17
PH IIA - Mill & Resurface (sacrificial) - EB Outside Widening (SR528)No29-Mar-1711-Jun-17
PH IIA - Install Sign & Traffic Control Devices - EB Outside WideningNo20-Sep-1511-Jun-17
PH IIA - MOT Shift for Phase IIA - EB Outside WideningNo07-Sep-1611-Jun-17
PH IIB - Embankment - Ramp ONo14-Dec-1511-Jun-17
PH IIB - Stabilization - Ramp ONo18-May-1711-Jun-17
PH IIB - Base - Ramp ONo30-May-1711-Jun-17
PH IIA - Jack & Bore (42" (Sta 351+00 near Duke energy access platform) - Ramp ONo06-Jul-1611-Jun-17
PH IIB - Drainage - Ramp ONo26-Jul-1611-Jun-17
PH IIA - Temp Striping New Ramp Alignment - Ramp ONo07-Sep-1619-Jun-17
PH IIA - Construct Ramp O Diversion - Ramp ONo11-Jul-1611-Jun-17
PH IIA - Construct Ramp O Diversion - Ramp O (Tie in to EB)No07-Sep-1611-Jun-17
PH IIB - Mill & Resurface (sacrificial) - EB Outside Widening (SR528)No05-Apr-1711-Jun-17
PH IIB - Embankment (Int. Drive - Universal) - EB Outside WideningNo15-Sep-1610-Jul-17
PH IIB - Embankment (Universal - JYP) - EB Outside WideningNo03-Oct-1610-Jul-17
PH IIB - Embankment (Int. Drive - Universal) - at Toll FacilityNo10-Oct-1611-Jun-17
PH IIB - MISC. Demo - EB Outside WideningNo06-Feb-1711-Jun-17
PH IIB - Performance Turf, SOD - EB Outside WideningNo20-Mar-1710-Jul-17
PH IIB - Stabilization (Int. Drive - Universal) - EB Outside WideningNo03-Apr-1710-Jul-17
PH IIB - Stabilization (Universal - JYP) - EB Outside Widening - (STA 291 to 320)No17-Mar-1711-Jun-17
PH IIB - Stabilization (Universal - JYP) - EB Outside Widening - (STA 320 to 332)Yes17-Mar-1711-Jun-17
PH IIB - Base (Universal - JYP) - EB Outside Widening - LR - (STA 320 to 332)Yes01-May-1711-Jun-17
PH IIB - Drainage (Int. Drive - Universal) - EB Outside Widening (SR528)No07-Nov-1611-Jun-17
PH IIB - Drainage (Universal - JYP) - EB Outside Widening (SR528)No20-Mar-1711-Jun-17
PH IIB - Gutter Drainage - STA 228 - 248 (EB Outside)No18-May-1710-Jul-17
PH IIB - Gutter Drainage - STA 280 - 299 (EB Outside)No08-May-1710-Jul-17
PH IIB - Gutter Drainage - STA 326 - 336 (EB Outside)No05-Apr-1710-Jul-17
PH IIB - Construct Crane Access - EB Outside Widening (Bridge over International DR)No18-Jul-1611-Jun-17
PH IIB - Test Pile - EB Outside Widening (Bridge over universal BLVD)No10-Oct-1611-Jun-17
PH IIB - Temp Sheet Pile - EB Outside Widening (Bridge over universal BLVD)No17-Oct-1611-Jun-17
PH IIB - Demo Traffic Rails - EB Outside Widening (Bridge over Shingle Creek)No10-Oct-1611-Jun-17
PH IIB - Production Pile - EB Outside Widening (Bridge over universal BLVD)No17-Oct-1611-Jun-17
PH IIB - Wall Bent 1 - EB Outside Widening (Bridge 750629 Ramp S over JYP)No30-Jan-1711-Jun-17
PH IIB - Demo Traffic Rails - EB Outside Widening (Bridge over International DR)No12-Apr-1711-Jun-17
PH IIB - Pier 2, (F/R/P)(Footer, Column & Pier Cap) - EB Outside Widening (Bridge over Universal BLVD)No31-Oct-1611-Jun-17
PH IIB - End Bent 1 - EB Outside Widening (Bridge 750629 Ramp S over JYP)No24-Jan-1711-Jun-17
PH IIB - Curing for Pier 2, (Footer, Column & Pier Cap) - EB Outside Widening (Bridge over Universal BLVD)No08-Dec-1611-Jun-17
PH IIB - Removal of Concrete Forms Pier 2, (Footer, Column & Pier Cap) - EB Outside Widening (Bridge over Universal BLVNo15-Dec-1611-Jun-17
PH IIB - Pier 2, 3, (F/R/P)(Pile Cap) - EB Outside Widening (Bridge over Shingle Creek)No07-Nov-1611-Jun-17
PH IIB - Temp Sheet Pile Removal - EB Outside Widening (Bridge over universal BLVD)No15-Dec-1611-Jun-17
PH IIB - Wall Bent 5 - EB Outside Widening (Bridge 750629 Ramp S over JYP)No13-Jan-1711-Jun-17
PH IIB - Construct Crane Access - EB Outside Widening (Bridge 750629 Ramp S over JYP)No04-Jan-1611-Jun-17
PH IIB - Test Pile (H Piles) - EB Outside Widening (Bridge 750629 Ramp S over JYP)No05-Jan-1611-Jun-17
PH IIB - Temp Sheet Pile - EB Outside Widening (Bridge 750629 Ramp S over JYP)No17-Mar-1611-Jun-17
PH IIB - Curing Pier 2, 3, (Pile Cap) - EB Outside Widening (Bridge over Shingle Creek)No10-Jan-1711-Jun-17
PH IIB - Production Pile (H Piles) (1-31) - EB Outside Widening (Bridge 750629 Ramp S over JYP)No09-Feb-1611-Jun-17
PH IIB - End Bent 5 - EB Outside Widening (Bridge 750629 Ramp S over JYP)No10-Jan-1711-Jun-17
PH IIB - Production Pile (H Piles) (32-62) -EB Outside Widening (Bridge 750629 Ramp S over JYP)No18-Apr-1611-Jun-17
PH IIB - Removal concrete form for Pier 2, 3, (Pile Cap) - EB Outside Widening (Bridge over Shingle CrNo20-Jan-1711-Jun-17
PH IIB - Pier 2, 3, 4 (F/R/P)(Footer, Column) - EB Outside Widening (Bridge 750629 Ramp S over JYP)No18-Mar-1611-Jun-17
PH IIB - Wall Bent 1 - EB Outside Widening (Bridge over Shingle Creek)No11-Jan-1711-Jun-17
PH IIB - Curing for Pier 2, 3, 4(Footer, Column & Pier Cap) - EB Outside Widening (Bridge 750629 Ramp S over JYP)No14-Nov-1611-Jun-17
PH IIB - Remove of Concrete Form Pier 2, 3, 4 (Footer, Column & Pier Cap) - EB Outside Widening (Bridge 750629 Ramp S ovNo15-Sep-1611-Jun-17
PH IIB - End Bent 1 - EB Outside Widening (Bridge over Shingle Creek)No11-Jan-1711-Jun-17
PH IIB - Temp Sheet Pile Removal - EB Outside Widening (Bridge 750629 Ramp S over JYP)No12-Aug-1611-Jun-17
PH IIB - Construct Crane Access - EB Outside Widening (Bridge over Shingle Creek)No01-Aug-1611-Jun-17
PH IIB - Set Beams - EB Outside Widening (Bridge 750629 Ramp S over JYP)No13-Feb-1711-Jun-17
PH IIB - Superstructure Deck SIP & Start Rebar - EB Outside Widening (Bridge 750629 Ramp S over JYP)No17-Feb-1711-Jun-17
PH IIB - Temp Sheet Pile - EB Outside Widening (Bridge over International DR)No13-Jun-1611-Jun-17
PH IIB - Production Pile (Concrete) - EB Outside Widening (Bridge over Shingle Creek)No17-Oct-1611-Jun-17
PH IIB - Wall Bent 4 - EB Outside Widening (Bridge over Shingle Creek)No26-Jan-1711-Jun-17
PH IIB - Gravity Wall @ Shingle Creek - EB Outside Widening (Bridge over Shingle Creek)No16-May-1611-Jun-17
PH IIB - End Bent 4 - EB Outside Widening (Bridge over Shingle Creek)No13-Jan-1711-Jun-17
PH IIB - Rip Rap Under Bridge - EB Outside Widening (Bridge over Shingle Creek)No02-Dec-1611-Jun-17
PH IIB - Demo Traffic Rails - EB Outside Widening (Bridge over universal BLVD)No10-Apr-1711-Jun-17
PH IIB - Superstructure Deck Finish Rebar\Set screed\Pouring - EB Outside Widening (Bridge 750629 Ramp S over JYP)No10-Mar-1711-Jun-17
PH IIB - Production Pile - EB Outside Widening (Bridge over International DR)No01-May-1611-Jun-17
PH IIB - End Bent 1 - EB Outside Widening (Bridge over universal BLVD)No06-Jun-1716-Jun-17
PH IIB - Set Beams - EB Outside Widening (Bridge over Shingle Creek)No06-Feb-1711-Jun-17
PH IIB - Wall Bent 3 - EB Outside Widening (Bridge over universal BLVD)No08-Jun-1711-Jun-17
PH IIB - Approach Slabs - EB Outside Widening (Bridge 750629 Ramp S over JYP)No01-May-1711-Jun-17
PH IIB - End Bent 3 - EB Outside Widening (Bridge over universal BLVD)No31-May-1726-Jun-17
PH IIB - Lighting Conduit - EB Outside Widening (Bridge 750629 Ramp S over JYP)No17-May-1711-Jun-17
PH IIB - Traffic Railing (32") - EB Outside Widening (Bridge 750629 Ramp S over JYP)No19-May-1711-Jun-17
PH IIB - Superstructure Deck SIP & Start Rebar - EB Outside Widening (Bridge over Shingle Creek)No10-Feb-1711-Jun-17
PH IIB - Pier 2, (F/R/P) (Footer, Column & Pier Cap) - EB Outside Widening (Bridge over International DR)No13-Jun-1614-Jun-17
PH IIB - Grind and Groove - EB Outside Widening (Bridge 750629 Ramp S over JYP)No02-Jun-1711-Jun-17
PH IIB - Approach Slabs - EB Outside Widening (Bridge over Shingle Creek)No27-Mar-1711-Jun-17
PH IIB - Curing for Pier 2, (Footer, Column & Pier Cap) - EB Outside Widening (Bridge over International DR)No05-Aug-1621-Jun-17
PH IIB - Lighting Conduit - EB Outside Widening (Bridge over Shingle Creek)No20-Apr-1711-Jun-17
PH IIB - Traffic Railing (32") - EB Outside Widening (Bridge over Shingle Creek)No24-Apr-1711-Jun-17
PH IIB - Grind and Groove - EB Outside Widening (Bridge over Shingle Creek)No31-May-1711-Jun-17
PH IIB - Demo Bridge Deck - EB Outside Widening (Bridge over International DR)No24-Apr-1711-Jun-17
PH IIB - Demo Bridge Deck - EB Outside Widening (Bridge over universal BLVD)No24-Apr-1711-Jun-17
PH IIB - Demo Bridge Deck - EB Outside Widening (Bridge over Shingle Creek)No11-Oct-1611-Jun-17
PH IIB - Remove Beams - EB Outside Widening (Bridge over Shingle Creek)No11-Oct-1611-Jun-17
PH IIB - Demo Pile Cap - EB Outside Widening (Bridge over Shingle Creek)No12-Oct-1611-Jun-17
PH IIB - Extract Piles - EB Outside Widening (Bridge over Shingle Creek)No13-Oct-1611-Jun-17
PH IIB - Pier 2, 3, 4 (F/R/P)(Pier Cap) - EB Outside Widening (Bridge 750629 Ramp S over JYP)No06-Jul-1611-Jun-17
PH IIB- Removal of Concrete Forms for Pier 2, (Footer, Column & Pier Cap) - EB Outside Widening (Bridge over InternatioNo12-Aug-1621-Jun-17
PH IIB - Superstructure Deck (Finish Rebar\Set Screed\Pour) - EB Outside Widening (Bridge over Shingle Creek)No24-Feb-1711-Jun-17
PH IIB - Curing for End Bent 5 - EB Outside Widening (Bridge 750629 Ramp S over JYP)No30-Jan-1711-Jun-17
PH IIB - Curing for End Bent 4 - EB Outside Widening (Bridge over Shingle Creek)No27-Jan-1711-Jun-17
PH IIB - Temp Sheet Pile Removal - EB Outside Widening (Bridge over International DR)No26-Jul-1621-Jun-17
PH IIB - Construct Crane Access - EB Outside Widening (Bridge over universal BLVD)No22-Aug-1611-Jun-17
PH IIB - Set Temp Traffic Barriers - EB Outside WideningNo21-Mar-1711-Jun-17
PH IIB - Asphalt - Structural - Ramp I4- InterstateNo19-Dec-1607-Jul-17
PH IIB - Asphalt - Structural - Ramp UNo11-May-1705-Jul-17
PH IIB - Existing High Mast Removal (1-8)No01-Mar-1714-Jun-17
PH IIB - Existing High Mast Removal (9-18)No05-May-1714-Jun-17
PH IIB - Embankment - Ramp ENo28-Dec-1511-Jun-17
PH IIB - Embankment - Ramp S-1No23-May-1611-Jun-17
PH IIB - Embankment - Ramp ANo18-May-1611-Jun-17
PH IIB - Embankment - Ramp R-1No20-Mar-1712-Jun-17
PH IIB - Embankment - Ramp HNo28-Nov-1611-Jun-17
PH IIB - Embankment - Ramp R-2No20-Mar-1713-Jun-17
PH IIB - Embankment - Ramp I4- InterstateNo19-Dec-1607-Jul-17
PH IIB - Embankment - Ramp LNo03-Apr-1705-Jul-17
PH IIB - Embankment - Ramp UNo15-Dec-1512-Jun-17
PH IIB - Demo - Ramp ENo06-Mar-1711-Jun-17
PH IIB - Demo - Ramp R-1No21-Mar-1712-Jun-17
PH IIB - Demo - Ramp S-1No16-Jan-1711-Jun-17
PH IIB - Clear & Grub/Demo - Ramp ANo13-Jun-1611-Jun-17
PH IIB - Performance Turf, SOD - Ramp ANo13-Sep-1611-Jun-17
PH IIB - Demo - Ramp HNo07-Mar-1711-Jun-17
PH IIB - Demo - Ramp R-2No21-Mar-1711-Jun-17
PH IIB - Demo - Ramp I4- InterstateNo19-Dec-1607-Jul-17
PH IIB - Demo - Ramp LNo20-Mar-1711-Jun-17
PH IIB - Performance Turf, SOD - Ramp I4- InterstateNo19-Dec-1607-Jul-17
PH IIB - Demo - Ramp UNo29-Mar-1712-Jun-17
PH IIB - Guardrail (Roadway) - Ramp I4- InterstateNo19-Dec-1607-Jul-17
PH IIB - Install Drilled Shafts (14-35)No14-Sep-1611-Jun-17
PH IIB - Install Drilled Shafts (36-57)No03-May-1711-Jun-17
PH IIB - Install High Mast/Service (4-6)No27-Oct-1614-Jun-17
PH IIB - Install High Mast/Service (7-9)No07-Mar-1722-Jun-17
PH IIB - Install Conduit/Boxes (I-4 to International)No28-Sep-1611-Jun-17
PH IIB - Install Conduit/Boxes ( International to Univ)No24-Feb-1720-Jun-17
PH IIB - Install Conduit/Boxes (Univ to JYP)No27-Jul-1626-Jun-17
PH IIB - Install Conduit/Boxes (JYP to TPK)No26-Jul-1628-Jun-17
PH IIB - Remove Existing Sign Structures (2-4)No20-Mar-1714-Jun-17
PH IIB - Stabilization - Ramp ANo05-Jul-1611-Jun-17
PH IIB - Base - Ramp ANo14-Jul-1611-Jun-17
PH IIB - Stabilization - Ramp I4- InterstateNo19-Dec-1607-Jul-17
PH IIB - Base - Ramp I4- InterstateNo19-Dec-1607-Jul-17
PH IIB - Stabilization - Ramp UNo03-Apr-1705-Jul-17
PH IIB - Base - Ramp UNo12-Apr-1705-Jul-17
PH IIB - Shoulder Mount Light Pole/Service (International to Univ.) (20 EA) (A)No19-Dec-1605-Jul-17
PH IIB - Shoulder Mount Light Pole/Service (International to Univ.) (20 EA) (B)No27-Mar-1717-Jul-17
PH IIB - Shoulder Mount Light Pole/Service (International to Univ.) (20 EA) (C)No25-Apr-1727-Jul-17
PH IIB - Shoulder Mount Light Pole/Service (Univ. to JYP) (18 EA) (A)No27-Jul-1607-Sep-17
PH IIB - Shoulder Mount Light Pole/Service (Univ. to JYP) (19 EA)No10-May-1714-Sep-17
PH IIB - Shoulder Mount Light Pole/Service (Univ. to JYP) (18 EA) (B)No16-May-1722-Sep-17
PH IIB - Shoulder Mount Light Pole/Service (JYP to TPK) (20 EA) (A)No26-Jul-1629-Sep-17
PH IIB - Shoulder Mount Light Pole/Service (JYP to TPK) (20 EA) (B)No09-May-1604-Oct-17
PH IIB - Drainage - Ramp ENo22-May-1711-Jun-17
PH IIB - Drainage (Temp) - Ramp R-1No10-Apr-1712-Jun-17
PH IIB - Drainage - Ramp ANo13-Jun-1611-Jun-17
PH IIB - Drainage (Temp) - Ramp S-1No16-Jan-1711-Jun-17
PH IIB - Drainage (Temp) - Ramp HNo31-Jan-1711-Jun-17
PH IIB - Drainage (Temp) - Ramp R-2No20-Mar-1713-Jun-17
PH IIB - Drainage (Temp) - Ramp I4 InterstateNo19-Dec-1607-Jul-17
PH IIB - Drainage (Temp) - Ramp LNo19-Dec-1611-Jun-17
PH IIB - Drainage (Temp) - Ramp UNo19-Dec-1612-Jun-17
PH IIB - Drainage - Ramp R-2No17-Apr-1713-Jun-17
PH IIB - Set Temp Traffic Barriers (Shoulder) - Ramp ENo27-Feb-1711-Jun-17
PH IIB - Temp Striping New Ramp Alignment - Ramp ENo28-Feb-1711-Jun-17
PH IIB - Set Temp Traffic Barriers (Shoulder) - Ramp CNo16-Apr-1707-Jul-17
PH IIB - Set Temp Traffic Barriers (Shoulder) - Ramp I-1No16-Jan-1711-Jun-17
PH IIB - Set Temp Traffic Barriers (Shoulder) - Ramp I4- InterstateNo19-Dec-1607-Jul-17
PH IIB - Temp Striping New Ramp Alignment - Ramp I-1No23-Feb-1711-Jun-17
PH IIB - Set Temp Traffic Barriers (Shoulder) - Ramp HNo27-Feb-1711-Jun-17
PH IIB - Temp Striping New Ramp Alignment - Ramp HNo28-Feb-1711-Jun-17
PH IIB - Temp Striping New Ramp Alignment - Ramp R-2No13-Mar-1711-Jun-17
PH IIB - Set Temp Traffic Barriers (Shoulder) - Ramp R-2No09-Mar-1711-Jun-17
PH IIB - Temp Striping New Ramp Alignment - Ramp I4- InterstateNo19-Dec-1611-Jun-17
PH IIB - MOT Shift New Ramp Alignment - Ramp I4- InterstateNo19-Dec-1611-Jun-17
PH IIB - Set Temp Traffic Barriers (Shoulder) - Ramp LNo16-Jan-1711-Jun-17
PH IIB - Temp Striping New Ramp Alignment - Ramp LNo28-Feb-1711-Jun-17
PH IIB - Set Temp Traffic Barriers (Shoulder) - Ramp UNo16-Jan-1711-Jun-17
PH IIB - Temp Striping New Ramp Alignment - Ramp UNo09-Mar-1712-Jun-17
PH IIB - Temp Striping New Ramp Alignment - Ramp DNo10-Apr-1711-Jun-17
PH IIB - Set Temp Traffic Barriers (Shoulder) - Ramp DNo20-Mar-1711-Jun-17
PH IIB - Construct Ramp E Diversion - Ramp ENo07-Dec-1611-Jun-17
PH IIB - Construct Ramp I-1 Diversion - Ramp I-1No21-Nov-1611-Jun-17
PH IIB - Construct Ramp R-1 Diversion - Ramp R-1No06-Feb-1711-Jun-17
PH IIB - Construct Ramp R-2 Diversion - Ramps R-2No06-Feb-1711-Jun-17
PH IIB - Construct Ramp H Diversion - Ramp HNo06-Dec-1611-Jun-17
PH IIB - Construct Ramp L Diversion - Ramp LNo28-Jul-1611-Jun-17
PH IIB - Construct Ramp U Diversion - Ramp UNo04-Jan-1712-Jun-17
PH IIC - Embankment - Ramp S-2No04-Oct-1613-Jul-17
PH IIC - MOT Shift for New Ramp Alignment - Ramp CNo19-Dec-1604-Oct-17
PH IIC - Construct Ramp S-2 Diversion - Ramp S-2No15-Feb-1711-Jun-17
PH IID - Construct Crane Access - EB Outside Widening (Bridge over John Young PKWY)No29-Feb-1623-Jun-17
PH IID - Temp Sheet Pile - EB Outside Widening (Bridge over John Young PKWY)No18-Mar-1611-Jun-17
PH IID - Production Pile (H Piles) - EB Outside Widening (Bridge over John Young PKWY)No01-Mar-1614-Sep-17
PH IID - Pier 2, 3, 4 (F/R/P) (Footer & Column) - EB Outside Widening (Bridge over John Young PKWY)No18-Mar-1611-Jun-17
PH IID - Curing for Pier 2, 3, 4(Footer, Column & Pier Cap) - EB Outside Widening (Bridge over John Young PKWY)No21-Sep-1616-Oct-17
PH IID - Remove Concrete form for Pier 2, 3, 4(Footer, Column & Pier Cap) - EB Outside Widening (Bridge over JYP)No16-Sep-1616-Oct-17
PH IID - Temp Sheet Pile Removal - EB Outside Widening (Bridge over John Young PKWY)No05-May-1616-Oct-17
PH IID - Pier 2, 3, 4 (F/R/P) ( Pier Cap) - EB Outside Widening (Bridge over John Young PKWY)No08-Jul-1616-Oct-17
PH IIIA - Construct Ramp Diversion P - Ramp P (STA 2013+84 to 2005+50)No10-Jan-1711-Jun-17
PH IIIA - Jack & Bore - WB Outside Widening Area (SR528)No24-Apr-1712-Jun-17
PH IIIA - Construct Crane Access - WB Outside Widening Area (Bridge 750630 Ramp T over JYP)No12-Jan-1623-Jun-17
PH IIIA - Test Pile (H Piles) - WB Outside Widening Area (Bridge 750630 Ramp T over JYP)No07-Dec-1511-Jun-17
PH IIIA - Temp Sheet Pile - WB Outside Widening Area (Bridge 750630 Ramp T over JYP)No05-May-1611-Jun-17
PH IIIA - Production Pile (H Piles) (1-32) - WB Outside Widening Area (Bridge 750630 Ramp T over JYP)No04-Apr-1611-Jun-17
PH IIIA - Production Pile (H Piles) (33-65) - WB Outside Widening Area (Bridge 750630 Ramp T over JYP)No13-Apr-1623-Jun-17
PH IIIA - Pier 2, 3, 4 (F/R/P)(Footer, Column) - WB Outside Widening Area (Bridge 750630 Ramp T over JYP)No08-May-1623-Jun-17
PH IIIA - Wall Bent 1 - WB Outside Widening Area (Bridge 750630 Ramp T over JYP)No17-Mar-1723-Jun-17
PH IIIA - Curing for Pier 2, 3, 4 (Footer, Column & Pier Cap) - WB Outside Widening Area (Bridge 750630 Ramp T over JYP)No21-Sep-1623-Jun-17
PH IIIA - Remove Concrete Form Pier 2, 3, 4 (Footer, Column & Pier Cap) - WB Outside Widening Area (Bridge 750630 Ramp TNo16-Sep-1623-Jun-17
PH IIIA - Temp Sheet Pile Removal - WB Outside Widening Area (Bridge 750630 Ramp T over JYP)No11-Aug-1611-Jun-17
PH IIIA - End Bent 1 - WB Outside Widening Area (Bridge 750630 Ramp T over JYP)No15-Mar-1723-Jun-17
PH IIIA - Construct Crane Access - WB Outside Widening Area (Bridge over John Young PKWY)No05-Apr-1623-Jun-17
PH IIIA - Wall Bent 5 - WB Outside Widening Area (Bridge 750630 Ramp T over JYP)No13-Apr-1723-Jun-17
PH IIIA - Temp Sheet Pile - WB Outside Widening Area (Bridge over John Young PKWY)No25-May-1623-Jun-17
PH IIIA - Production Pile (H Piles) - WB Outside Widening Area (Bridge over John Young PKWY)No07-Apr-1611-Jun-17
PH IIIA - Pier 2, 3, 4 (F/R/P)(Footer, Column) - WB Outside Widening Area (Bridge over John Young PKWY)No26-May-1611-Jun-17
PH IIIA - Curing of Pier 2, 3, 4 (Footer, Column & Pier Cap) - WB Outside Widening Area (Bridge over John Young PKWY)No21-Sep-1617-Jul-17
PH IIIA - End Bent 5 - WB Outside Widening Area (Bridge 750630 Ramp T over JYP)No05-Apr-1723-Jun-17
PH IIIA - Remove Concrete Form for Pier 2, 3, 4(Footer, Column & Pier Cap) - WB Outside Widening Area (Bridge over JohnNo16-Sep-1617-Jul-17
PH IIIA - Curing for End Bent 5 - WB Outside Widening Area (Bridge 750630 Ramp T over JYP)No19-Apr-1723-Jun-17
PH IIIA - Temp Sheet Pile Removal - WB Outside Widening Area (Bridge over John Young PKWY)No10-Aug-1617-Jul-17
PH IIIA - Set Beams - WB Outside Widening Area (Bridge 750630 Ramp T over JYP)No10-May-1723-Jun-17
PH IIIA - Superstructure Deck SIP & Start Rebar - WB Outside Widening Area (Bridge 750630 Ramp T over JYP)No15-May-1723-Jun-17
PH IIIA - Superstructure Deck Finish Rebar\Set Screed\ Pour - WB Outside Widening Area (Bridge 750630 Ramp T over JYP)No31-May-1711-Jun-17
PH IIIA - Pier 2, 3, 4 (F/R/P)(Pier Cap) - WB Outside Widening Area (Bridge 750630 Ramp T over JYP)No15-Aug-1623-Jun-17
PH IIIA - Pier 2, 3, 4 (F/R/P) (Pier Cap) - WB Outside Widening Area (Bridge over John Young PKWY)No08-Jul-1617-Jul-17
PH IIIB - Embankment - Ramp VNo18-May-1722-Nov-17
PH IIIB - Embankment - Ramp TNo28-Dec-1525-Sep-17
PH IIIB - Demo - Ramp VNo28-Mar-1707-Nov-17
PH IIIB - Install High Mast/Service (10-13)No14-Mar-1730-Jun-17
PH IIIB - Install Conduit/Boxes (JYP to TPK)No18-Jul-1606-Jul-17
PH IIIB - Shoulder Mount Light Pole/Service (International to Univ.) (10 EA)No19-Dec-1611-Dec-17
PH IIIB - Shoulder Mount Light Pole/Service (JYP to TPK) (20 EA) (A)No17-Oct-1628-Mar-18
PH IIIB - Shoulder Mount Light Pole/Service (JYP to TPK) (20 EA) (B)No17-Oct-1613-Apr-18
PH IIIB - Shoulder Mount Light Pole/Service (JYP to TPK) (20 EA) (C)No17-Oct-1601-May-18
PH IIIB - Drainage (Temp) - Ramp TNo19-Dec-1621-Sep-17
PH IIIB - Set Temp Traffic Barriers (Shoulder) - Ramp VNo19-Apr-1707-Nov-17
PH IIIB - Temp Striping New Ramp Alignment - Ramp VNo16-Mar-1707-Nov-17
PH IIIB - Construct Ramp V Diversion - Ramp VNo23-Jan-1714-Sep-17
PH IIIB - Construct Ramp K Diversion/Temp Pavement - Ramp KNo03-Apr-1714-Sep-17
PH IIIB - Surcharge/ Embankment 1 - WB Outside Widening AreaNo01-May-1714-Sep-17
PH IIIB - Surcharge/ Embankment 2 - WB Outside Widening AreaNo19-May-1714-Sep-17
PH IIIB - Embankment (JYP-Universal) - WB Outside Widening AreaNo16-Nov-1513-Jun-17
PH IIIB - Embankment (Universal - International) - WB Outside Widening AreaNo18-Apr-1614-Aug-17
PH IIIB - Pond Excav/Embank JYP to Universal - WB Outside WideningNo19-Sep-1614-Sep-17
PH IIIB - Drainage (JYP-Universal) - WB Outside Widening Area (SR528)No16-May-1611-Jun-17
PH IIIB - Drainage (Universal - International) - WB Outside Widening Area (SR528)No07-Mar-1614-Jun-17
PH IIIB - Construct Crane Access - WB Outside Widening Area (Bridge over International DR)No18-Jul-1611-Jun-17
PH IIIB - Production Pile - WB Outside Widening Area (Bridge over universal BLVD)No12-Sep-1616-Aug-17
PH IIIB - Pier 2, (F/R/P)(Footer, Column & Pier Cap) - WB Outside Widening Area (Bridge over Universal BLVD)No01-Nov-1616-Aug-17
PH IIIB - Curing for Pier 2, (Footer, Column & Pier Cap) - WB Outside Widening Area (Bridge over Universal BLVD)No08-Dec-1621-Aug-17
PH IIIB - Removal for Concrete Forms for Pier 2, (Footer, Column & Pier Cap) - WB Outside Widening Area (Bridge over UniNo15-Dec-1621-Aug-17
PH IIIB - Temp Sheet Pile Removal - WB Outside Widening Area (Bridge over universal BLVD)No16-Dec-1611-Jun-17
PH IIIB - Temp Sheet Pile - WB Outside Widening Area (Bridge over International DR)No27-Jun-1611-Jun-17
PH IIIB - Production Pile - WB Outside Widening Area (Bridge over International DR)No01-May-1611-Jun-17
PH IIIB - Pier 2, (F/R/P)(Footer, Column & Pier Cap) - WB Outside Widening Area (Bridge over International DR)No28-Jun-1618-Sep-17
PH IIIB - Construct Crane Access - WB Outside Widening Area (Bridge over universal BLVD)No15-Aug-1611-Aug-17
PH IIIB - Test Pile - WB Outside Widening Area (Bridge over universal BLVD)No08-Sep-1611-Jun-17
PH IIIB - Temp Sheet Pile - WB Outside Widening Area (Bridge over universal BLVD)No28-Oct-1611-Aug-17
PH IIIB - Temp Sheet Pile Removal - WB Outside Widening Area (Bridge over International DR)No27-Jul-1626-Sep-17
PH IIIC - Embankment - Ramp FNo05-Apr-1629-Dec-17
Fabricate and Deliver 506 Bridge Drainage SystemNo25-Jan-1711-Jun-17
Fabricate and Deliver 455 Structure Foundations Prestressed Concrete Piling 18" (Structures 750089 & 750216)No15-Feb-1611-Jun-17
Fabricate and Deliver 455 Structure Foundations Prestressed Concrete Piling 24" (Structure 750631-Shingle Creek)No21-Oct-1511-Jun-17
Fabricate and Deliver 455 Structure Foundations Steel Pile HP 14X89 (Structures 750088 and 750215 I-Drive)No15-Feb-1611-Jun-17
Fabricate and Deliver 455 Structure Foundations Steel Pile HP 12X53 (Structure 750629-Ramp S JYP)No17-Jan-1611-Jun-17
Fabricate and Deliver 455 Structure Foundations Steel Pile HP 12X53 (Structures 750091 and 750218-JYP)No16-Nov-1511-Jun-17
Fabricate and Deliver 455 Structure Foundations Steel Pile HP 12X53 (Structure 750630-Ramp T JYP)No16-Nov-1511-Jun-17
Fabricate and Deliver 400 Concrete Structures (Bearing Pads)No09-Mar-1611-Jun-17
Fabricate and Deliver 450 Precast Prestressed Florida I Beam 36" (Structures 750088 & 750215- I-Drive)No21-Feb-1611-Jun-17
Fabricate and Deliver 450 Precast Prestressed Florida I Beam 45" (Structures 750089, & 750216- Universal/Orangewood)No21-Feb-1611-Jun-17
Fabricate and Deliver 450 Precast Prestressed Beams TY II (Structures 750631-Shingle Creek)No21-Feb-1611-Jun-17
Fabricate and Deliver 450 Precast Prestressed Florida I Beam 36" (Structures 750091 & 750218- JYP)No21-Feb-1611-Jun-17
Fabricate and Deliver 455 Temp Sheet Pile/CriticalNo26-Jan-1611-Jun-17
Fabricate and Deliver 450 Precast Prestressed Florida I Beam 36" (Structures 750629 Ramp S JYP & 750630 Ramp T JYP)No21-Feb-1611-Jun-17
Fabricate and Deliver 455 Auger Cast Piles (w/noise wall submittal)No26-Jan-1611-Jun-17
Fabricate and Deliver 534 Noise and Perimeter WallsNo01-Feb-1611-Jun-17
Fabricate and Deliver 548 Retaining/MSE Wall SystemsNo18-Jul-1611-Jun-17
Fabricate and Deliver 641 Prestressed Concrete PolesNo22-Aug-1611-Jun-17
Fabricate and Deliver 700 Highway Signing (Single, Multi, Panel, and Overhead)No09-Mar-1711-Jun-17
Fabricate and Deliver 05500 Metal FabricationsNo20-Mar-1711-Jun-17
Fabricate and Deliver 133420 Pre-Engineered Precast Concrete StructureNo27-Feb-1711-Jun-17
Fabricate and Deliver 263213 Engine GeneratorNo22-May-1711-Jun-17
Fabricate and Deliver 633 Communication CableNo22-Aug-1611-Jun-17
Fabricate and Deliver 635 Pull, Splice, & Junction BoxesNo22-Aug-1611-Jun-17
Fabricate and Deliver 033000 Cast-In-Place ConcreteNo15-May-1711-Jun-17
Fabricate and Deliver 081100 Metal Doors and FramesNo16-Jan-1711-Jun-17
Fabricate and Deliver 099100 Painting Product Data and SampleNo16-Jan-1711-Jun-17
Fabricate and Deliver 231113 Fuel Oil PipingNo05-May-1711-Jun-17
Fabricate and Deliver 231323 Aboveground Diesel Storage Tank and PipingNo05-May-1711-Jun-17
Fabricate and Deliver 232000 Piping and SpecialtiesNo25-Jan-1711-Jun-17
Fabricate and Deliver 233113 Ductwork Product Data and Shop DrawingNo22-May-1711-Jun-17
Fabricate and Deliver 238119 Packaged Air ConditionersNo17-Jan-1711-Jun-17
Fabricate and Deliver 260536 Cable TraysNo09-Feb-1711-Jun-17
Fabricate and Deliver 264113 Lighting Protection System Product Data and Shop DrawingNo19-Apr-1711-Jun-17
Fabricate and Deliver 682 CCTV CameraNo22-Aug-1611-Jun-17
Fabricate and Deliver 781 DMSNo18-May-1711-Jun-17
Fabricate and Deliver 783 ITS Fiber Optic CableNo22-Aug-1611-Jun-17
Fabricate and Deliver 784 ITS Managed Ethernet Hub SwitchNo22-Aug-1611-Jun-17
Fabricate and Deliver 685 ITS Uninterruptible Power Source (UPS)No22-Aug-1611-Jun-17
Fabricate and Deliver 262913 ITS Standby Generator Product Data and Shop DrawingNo22-Aug-1611-Jun-17
Fabricate and Deliver 400 Concrete Structures (SIP Metal Forms)No14-Dec-1511-Jun-17
Prepare and Submit 506 Bridge Drainage SystemNo08-Aug-1611-Jun-17
Prepare and Submit 455 Pile Installation Plan (Structures 750089 & 750216-Universal/Orangewood)No20-Sep-1511-Jun-17
Prepare and Submit 455 Pile Installation Plan (Structures 750091 & 750218-John Young Parkway)No20-Sep-1511-Jun-17
Prepare and Submit 455 Pile Installation Plan (Structure 750629- Ramp S JYP)No20-Sep-1511-Jun-17
Prepare and Submit 455 Pile Installation Plan (Structure 750630- Ramp T JYP)No20-Sep-1511-Jun-17
Prepare and Submit Precast ErectionNo03-Jun-1611-Jun-17
Prepare and Submit 400 Concrete Structures (Bearing Pads)No11-Jan-1611-Jun-17
Prepare and Submit 450 Precast Prestressed Florida I Beam 36" (Structures 750088 & 750215- I-Drive)No01-Oct-1511-Jun-17
Prepare and Submit 450 Precast Prestressed Florida I Beam 45" (Structures 750089, & 750216- Universal/Orangewood)No01-Oct-1511-Jun-17
Prepare and Submit 450 Precast Prestressed Beams TY II (Structures 750631-Shingle Creek)No01-Oct-1511-Jun-17
Prepare and Submit 450 Precast Prestressed Florida I Beam 36" (Structures 750091 & 750218- JYP)No01-Oct-1511-Jun-17
Prepare and Submit 450 Precast Prestressed Florida I Beam 36" (Structures 750629 Ramp S JYP & 750630 Ramp T JYP)No20-Sep-1511-Jun-17
Prepare and Submit 455 Auger Cast Piles (w/noise wall submittal)No07-Oct-1511-Jun-17
Prepare and Submit 534 Noise and Perimeter WallsNo21-Oct-1511-Jun-17
Prepare and Submit 548 Retaining/MSE Wall SystemsNo17-Apr-1611-Jun-17
Prepare and Submit 641 Prestressed Concrete PolesNo15-Feb-1611-Jun-17
Prepare and Submit 646 Aluminum Pedestal PolesNo20-Mar-1711-Jun-17
Prepare and Submit 650 Traffic SignalsNo15-Feb-1611-Jun-17
Prepare and Submit 700 Highway Signing (Single, Multi, Panel, and Overhead)No11-Jan-1611-Jun-17
Prepare and Submit 05500 Metal FabricationsNo16-May-1611-Jun-17
Prepare and Submit 133420 Pre-Engineered Precast Concrete StructureNo03-Jun-1611-Jun-17
Prepare and Submit 263213 Engine GeneratorNo18-Nov-1611-Jun-17
Prepare and Submit 633 Communication CableNo15-Feb-1611-Jun-17
Prepare and Submit 635 Pull, Splice, & Junction BoxesNo18-Jan-1611-Jun-17
Prepare and Submit 653 Pedestrian SignalsNo20-Mar-1711-Jun-17
Prepare and Submit 663 Signal Priority and Preemption SystemsNo28-Jan-1611-Jun-17
Prepare and Submit 665 Pedestrian DetectorNo20-Mar-1711-Jun-17
Prepare and Submit 033000 Cast-In-Place ConcreteNo26-Sep-1611-Jun-17
Prepare and Submit 042200 MasonryNo20-Feb-1711-Jun-17
Prepare and Submit 081100 Metal Doors and FramesNo19-Oct-1611-Jun-17
Prepare and Submit 099100 Painting Product Data and SampleNo19-Oct-1611-Jun-17
Prepare and Submit 101400 SignageNo27-Feb-1711-Jun-17
Prepare and Submit 231113 Fuel Oil PipingNo13-Feb-1711-Jun-17
Prepare and Submit 231323 Aboveground Diesel Storage Tank and PipingNo13-Feb-1711-Jun-17
Prepare and Submit 232000 Piping and SpecialtiesNo16-Jan-1711-Jun-17
Prepare and Submit 233113 Ductwork Product Data and Shop DrawingNo20-Feb-1711-Jun-17
Prepare and Submit 238119 Packaged Air ConditionersNo09-Jan-1711-Jun-17
Prepare and Submit 260536 Cable TraysNo16-Jan-1711-Jun-17
Prepare and Submit 264113 Lighting Protection System Product Data and Shop DrawingNo20-Mar-1711-Jun-17
Prepare and Submit 682 CCTV CameraNo01-Aug-1611-Jun-17
Prepare and Submit 781 DMSNo22-Aug-1611-Jun-17
Prepare and Submit 783 ITS Fiber Optic CableNo08-Feb-1611-Jun-17
Prepare and Submit 660 ITS Vehicle Detection SystemNo01-Aug-1611-Jun-17
Prepare and Submit 684 ITS Managed Ethernet Hub SwitchNo01-Aug-1611-Jun-17
Prepare and Submit 785 ITS Uninterruptible Power Source (UPS)No01-Aug-1611-Jun-17
Prepare and Submit 639 ITS Standby Generator Product Data and Shop DrawingNo21-Mar-1611-Jun-17
Prepare and Submit 400 Concrete Structures (SIP Metal Forms)No20-Sep-1511-Jun-17
Review and Approve 506 Bridge Drainage SystemNo19-Jan-1711-Jun-17
Review and Approve 455 Pile Installation Plan (Structures 750089 & 750216-Universal/Orangewood)No27-Sep-1511-Jun-17
Review and Approve 455 Pile Installation Plan (Structures 750091 & 750218-John Young Parkway)No27-Sep-1511-Jun-17
Review and Approve 455 Pile Installation Plan (Structure 750629- Ramp S JYP)No27-Sep-1511-Jun-17
Review and Approve 455 Pile Installation Plan (Structure 750630- Ramp T JYP)No27-Sep-1511-Jun-17
Review and Approve 400 Concrete Structures (Bearing Pads)No02-Mar-1611-Jun-17
Review and Approve 450 Precast Prestressed Florida I Beam 36" (Structures 750088 & 750215- I-Drive)No18-Oct-1511-Jun-17
Review and Approve 450 Precast Prestressed Florida I Beam 45" (Structures 750089, & 750216- Universal/Orangewood)No18-Oct-1511-Jun-17
Review and Approve 450 Precast Prestressed Beams TY II (Structures 750631-Shingle Creek)No18-Oct-1511-Jun-17
Review and Approve 450 Precast Prestressed Florida I Beam 36" (Structures 750091 & 750218- JYP)No18-Oct-1511-Jun-17
Review and Approve 450 Precast Prestressed Florida I Beam 36" (Structures 750629 Ramp S JYP & 750630 Ramp T JYP)No18-Oct-1511-Jun-17
Review and Approve 455 Auger Cast Piles (w/noise wall submittal)No21-Oct-1511-Jun-17
Review and Approve 534 Noise and Perimeter WallsNo21-Oct-1511-Jun-17
Review and Approve 548 Retaining/MSE Wall SystemsNo29-Apr-1611-Jun-17
Review and Approve 641 Prestressed Concrete PolesNo16-Feb-1611-Jun-17
Review and Approve 646 Aluminum Pedestal PolesNo23-Mar-1711-Jun-17
Review and Approve 650 Traffic SignalsNo23-Mar-1724-Jun-17
Review and Approve 700 Highway Signing (Single, Multi, Panel, and Overhead)No18-Jan-1611-Jun-17
Review and Approve 05500 Metal FabricationsNo08-Jun-1611-Jun-17
Review and Approve 133420 Pre-Engineered Precast Concrete StructureNo12-Jan-1711-Jun-17
Review and Approve 263213 Engine GeneratorNo01-Feb-1711-Jun-17
Review and Approve 633 Communication CableNo16-Feb-1611-Jun-17
Review and Approve 635 Pull, Splice, & Junction BoxesNo16-Feb-1611-Jun-17
Review and Approve 653 Pedestrian SignalsNo23-Mar-1711-Jun-17
Review and Approve 663 Signal Priority and Preemption SystemsNo16-Feb-1615-Jun-17
Review and Approve 665 Pedestrian DetectorNo23-Mar-1711-Jun-17
Review and Approve 033000 Cast-In-Place ConcreteNo26-Oct-1611-Jun-17
Review and Approve 081100 Metal Doors and FramesNo26-Oct-1611-Jun-17
Review and Approve 099100 Painting Product Data and SampleNo26-Oct-1611-Jun-17
Review and Approve 101400 SignageNo29-Mar-1711-Jun-17
Review and Approve 231113 Fuel Oil PipingNo21-Apr-1711-Jun-17
Review and Approve 231323 Aboveground Diesel Storage Tank and PipingNo28-Mar-1711-Jun-17
Review and Approve 232000 Piping and SpecialtiesNo18-Jan-1711-Jun-17
Review and Approve 233113 Ductwork Product Data and Shop DrawingNo22-May-1711-Jun-17
Review and Approve 238119 Packaged Air ConditionersNo12-Jan-1711-Jun-17
Review and Approve 260536 Cable TraysNo18-Jan-1711-Jun-17
Review and Approve 264113 Lighting Protection System Product Data and Shop DrawingNo28-Mar-1711-Jun-17
Review and Approve 682 CCTV CameraNo03-Aug-1611-Jun-17
Review and Approve 781 DMSNo25-Aug-1611-Jun-17
Review and Approve 633 ITS Fiber Optic CableNo26-Jul-1611-Jun-17
Review and Approve 660 ITS Vehicle Detection SystemNo03-Aug-1611-Jun-17
Review and Approve 684 ITS Managed Ethernet Hub SwitchNo03-Aug-1611-Jun-17
Review and Approve 685 ITS Uninterruptible Power Source (UPS)No03-Aug-1611-Jun-17
Review and Approve 639 ITS Standby Generator Product Data and Shop DrawingNo30-Mar-1611-Jun-17
Review and Approve 400 Concrete Structures (SIP Metal Forms)No30-Nov-1511-Jun-17
Begin Electrical (Stub Outs & Site Electrical)No23-May-1711-Jun-17
Install Upright 2 D.S.No22-Mar-1711-Jun-17
Install Upright 3 D.S.No24-Mar-1711-Jun-17
AS Build D.S.No30-Mar-1711-Jun-17
Fabricate and Deliver Precast ErectionNo30-Jan-1711-Jun-17
Review and Approve Precast ErectionNo12-Jan-1711-Jun-17
ATT FloridaNo29-Oct-1511-Jun-17
Bright houseNo27-Oct-1511-Jun-17
Duke Energy Distribution (A)No01-Dec-1511-Jun-17
Duke Energy Distribution (B)No30-Nov-1511-Jun-17
Duke Energy Transmission Phase 1No12-Oct-1511-Jun-17
OUC Remove Water Main @ JYP (Sta 325 - 329)No29-Oct-1511-Jun-17
SummitNo29-Oct-1511-Jun-17
TECONo07-Dec-1511-Jun-17
VerizonNo07-Dec-1511-Jun-17

Relationship type and calendar context now qualify how lag is interpreted.

This table lists nonzero relationship lag. Its timing meaning depends on the relationship type, so a negative value does not always mean that a successor starts before its predecessor finishes.

Highlighted in red are negative lag values. Display conversion uses the predecessor activity calendar. P6 scheduling behavior can instead follow the relationship-lag calendar option saved with the schedule, so use the raw relationship and P6 settings when exact date reproduction is required.

Activity IDActivity DescriptionOn LPRelationship TypePredecessor Activity IDPredecessor Activity DescriptionRelationship Lag
PH IV - MOT Shift for Phase - EB Median WideningNoSSPH IV - Temp Striping for Phase - EB Median Widening1

Calendars control working time, holidays, activity dates, and resource availability. Review their weekly hours, exceptions, assignments, and default status in project context.

Highlighted in green are project default and global/base default calendars, if any.
Highlighted in red are calendars not assigned to an activity. An unused calendar may be obsolete, intentionally retained, or used elsewhere in the project setup; confirm before changing it.

IDScopeDefaultLinked ActivitiesNameLast updated
9959BaseNo905 day FDOT with Holiday22-Aug-16
1559BaseNo-5 day FDOT with Holidays18-May-13
8489BaseNo-Standard 7-Day Workweek19-Sep-16
21490ProjectYes836Beachline 5-days with Holidays15-Dec-15
21489ProjectNo197Beachline 7-Day Workweek15-Dec-15
21491ProjectNo89Beachline Night-Shift 5-Days with Holidays15-Dec-15

1559: 5 day FDOT with Holidays

Day Hours: 8, Week Hours: 40, Month Hours: 172, Year Hours: 2024

There are non-working days going back prior to 01-Jan-2020. You should consider migrating to a newer calendar.

Weekly Schedule

DayTime Slots
SunNo Work
Mon08:00-12:00, 13:00-17:00
Tue08:00-12:00, 13:00-17:00
Wed08:00-12:00, 13:00-17:00
Thu08:00-12:00, 13:00-17:00
Fri08:00-12:00, 13:00-17:00
SatNo Work

Holidays and No Work days

DayHoliday
01-Jan-20New Year's Day
25-May-20Memorial Day
03-Jul-20-
07-Sep-20Labor Day
26-Nov-20Thanksgiving Day
27-Nov-20-
25-Dec-20Christmas Day
01-Jan-21New Year's Day

8489: Standard 7-Day Workweek

Day Hours: 8, Week Hours: 56, Month Hours: 172, Year Hours: 2000

There are non-working days going back prior to 01-Jan-2020. You should consider migrating to a newer calendar.

Weekly Schedule

DayTime Slots
Sun08:00-16:00
Mon08:00-16:00
Tue08:00-16:00
Wed08:00-16:00
Thu08:00-16:00
Fri08:00-16:00
Sat08:00-16:00

Holidays and No Work days

[no data]

9959: 5 day FDOT with Holiday

Day Hours: 8, Week Hours: 40, Month Hours: 172, Year Hours: 2024

There are non-working days going back prior to 01-Jan-2020. You should consider migrating to a newer calendar.

Weekly Schedule

DayTime Slots
SunNo Work
Mon08:00-12:00, 13:00-17:00
Tue08:00-12:00, 13:00-17:00
Wed08:00-12:00, 13:00-17:00
Thu08:00-12:00, 13:00-17:00
Fri08:00-12:00, 13:00-17:00
SatNo Work

Holidays and No Work days

DayHoliday
01-Jan-20New Year's Day
20-Jan-20Martin Luther King Jr. Day
25-May-20Memorial Day
03-Jul-20-
07-Sep-20Labor Day
11-Nov-20Veterans Day
26-Nov-20Thanksgiving Day
27-Nov-20-
25-Dec-20Christmas Day
01-Jan-21New Year's Day

21489: Beachline 7-Day Workweek

Day Hours: 8, Week Hours: 56, Month Hours: 172, Year Hours: 2000

Weekly Schedule

DayTime Slots
Sun08:00-16:00
Mon08:00-16:00
Tue08:00-16:00
Wed08:00-16:00
Thu08:00-16:00
Fri08:00-16:00
Sat08:00-16:00

Holidays and No Work days

[no data]

21490: Beachline 5-days with Holidays

Day Hours: 8, Week Hours: 40, Month Hours: 172, Year Hours: 2024

There are non-working days going back prior to 01-Jan-2020. You should consider migrating to a newer calendar.

Weekly Schedule

DayTime Slots
SunNo Work
Mon08:00-12:00, 13:00-17:00
Tue08:00-12:00, 13:00-17:00
Wed08:00-12:00, 13:00-17:00
Thu08:00-12:00, 13:00-17:00
Fri08:00-12:00, 13:00-17:00
SatNo Work

Holidays and No Work days

DayHoliday
01-Jan-20New Year's Day
20-Jan-20Martin Luther King Jr. Day
25-May-20Memorial Day
03-Jul-20-
07-Sep-20Labor Day
11-Nov-20Veterans Day
26-Nov-20Thanksgiving Day
27-Nov-20-
25-Dec-20Christmas Day
01-Jan-21New Year's Day

21491: Beachline Night-Shift 5-Days with Holidays

Day Hours: 8, Week Hours: 40, Month Hours: 172, Year Hours: 2024

There are non-working days going back prior to 01-Jan-2020. You should consider migrating to a newer calendar.

Weekly Schedule

DayTime Slots
SunNo Work
Mon00:00-06:00, 22:00-00:00
Tue00:00-06:00, 22:00-00:00
Wed00:00-06:00, 22:00-00:00
Thu00:00-06:00, 22:00-00:00
Fri00:00-06:00, 22:00-00:00
SatNo Work

Holidays and No Work days

DayHoliday
01-Jan-20New Year's Day
20-Jan-20Martin Luther King Jr. Day
25-May-20Memorial Day
03-Jul-20-
07-Sep-20Labor Day
11-Nov-20Veterans Day
26-Nov-20Thanksgiving Day
27-Nov-20-
25-Dec-20Christmas Day
01-Jan-21New Year's Day

Each row represents a unique resource and summarizes how it is being utilized across activities.

Highlighted in red are resources that P6 will not allow you to assign tasks to (i.e. those not cost‑linked or not auto‑compute‑active).
The Assignable in P6 column shows "Yes" for resources P6 treats as assignable and "No" for those it hides.

TypeIDNameAssigned ActivitiesAssignable in P6
LaborAsphaltAsphalt team71Yes
LaborBaseRoad base team81Yes
LaborCarrCarr24Yes
LaborCIFCIF2Yes
LaborConcreteConcrete team254Yes
LaborDemoDemo Team72Yes
LaborDrainageDrainage team54Yes
LaborElectricalElectrical team16Yes
LaborEmbankmentEmbankment58Yes
LaborExcavationExcavation team23Yes
LaborJVDJVD23Yes
LaborMOTTraffic Control Team107Yes
LaborPaffPaff26Yes
LaborPilePile team64Yes
LaborSlagterSlagter26Yes
LaborStabilizationStabilization team69Yes
LaborUS&SUS & S101Yes
MatTPKCOTPK COST1041Yes

This report compares each resource's scheduled workload against their available capacity on a month-by-month basis. We calculate capacity using each resource's work calendar (their working days and hours), shift schedules, and defined production or labor rates. Remaining activity work is then spread across the months that the activity is scheduled to run. Whenever the total assigned units in a given month exceed the resource's calculated capacity, that resource is flagged as overallocated.

Demand is the total work assigned to a resource in a month.
Limit is that resource's available capacity.
Overage is the actual resource overallocation - the amount by which Demand exceeds Limit.

Resource overallocation can lead to missed deadlines, reduced quality, and team burnout. By clearly highlighting these overbooked periods, this report helps you take corrective action: adjust task start or finish dates, redistribute work to less-busy teams, extend deadlines, or bring in additional support.

Resource IDResource NameMonthDemandLimitOverageActivities
AsphaltAsphalt teamJun-2017468176292IBEBM-RW330 = 60, IBWBM-RW220 = 45, IBWBM-RW230 = 50, IIAR-AP100 = 20, IIBEBO-AP140 = 200, IIBR-AP110 = 20, IIBR-AP151 = 10, IICR-SP130 = 53, IIIAWBO-AP100 = 10
Jul-2017398168230IBR-AP110 = 50, IIBEBO-AP130 = 200, IIBR-AP130 = 20, IIBR-AP140 = 20, IIBR-AP150 = 20, IIBR-AP170 = 20, IIBR-AP180 = 1, IICR-AP100 = 20, IICR-SP130 = 47
Aug-201719518411IIBEBO-AP120 = 175, IICR-AP120 = 20
Sep-201723516867IIBEBO-AP110 = 200, IIBEBO-AP120 = 25, IIBR-AP120 = 10
Oct-2017596176420IIBR-AP100 = 40, IIBR-AP120 = 30, IIDEBO-RW150 = 143, IIIBR-AP100 = 20, IIIBR-AP140 = 20, IIIBR-AP150 = 20, IIICR130 = 83, IIICR170 = 40, IIICR180 = 200
Nov-2017434176258IIDEBO-RW150 = 78, IIIBWBO-AP100 = 80, IIICR130 = 117, IIICR170 = 160
Dec-2017610168442IIIBR-AP110 = 20, IIIBR-AP120 = 20, IIIBWBO-AP100 = 20, IIICR110 = 150, IIICR140 = 200, IIICR200 = 200
Jan-2018567184383IIIBR-AP130 = 20, IIIBR-AP160 = 20, IIICR-AP100 = 20, IIICR110 = 50, IIICR120 = 107, IIICR160 = 150, IIICR190 = 200
Feb-2018317160157IIIBWBO-AP110 = 100, IIICR-AP110 = 20, IIICR120 = 93, IIICR150 = 53, IIICR160 = 50
Aug-2018310184126IVEBM-AP100 = 30, IVEBO-AP100 = 80, IVEBO-PM110 = 50, IVWBM-AP100 = 40, IVWBO-AP100 = 60, IVWBO-PM110 = 50
CarrCarrJun-2017534176358IIBR-ITS10 = 70, IIBR-ITS20 = 40, IIBR-ITS30 = 20, IIBR-ITS40 = 4, IIIBR-ITS1000 = 200, IIIBR-ITS1010 = 100, IIIBR-ITS1020 = 100
Jul-2017356168188IIBR-ITS40 = 6, IIBR-ITS50 = 90, IIIBR-ITS1010 = 100, IIIBR-ITS1020 = 100, IIIBR-ITS80 = 60
Aug-201723018446IIBR-ITS50 = 110, IIBR-ITS60 = 120
Sep-201720016832IIBR-ITS60 = 80, IIIBR-ITS90 = 120
Oct-201725517679IIBR-ITS70 = 175, IIIBR-ITS90 = 80
Nov-2017285176109IIBR-ITS70 = 25, IIBR-ITS80 = 200, IIBR-ITS90 = 60
Dec-2017280168112IIBR-ITS90 = 140, IIIBR-ITS100 = 140
Feb-201820016040IIIBR-ITS110 = 100, IIIBR-ITS130 = 100
Mar-201822017644IIIBR-ITS130 = 100, IIIBR-ITS140 = 120
Apr-201821016842IIIBR-ITS140 = 80, IIIBR-ITS150 = 100, IIIBR-ITS160 = 30
May-201823018446IIIBR-ITS160 = 70, IIIBR-ITS170 = 100, IIIBR-ITS180 = 60
Jun-201820016832IIIBR-ITS180 = 40, IIIBR-ITS190 = 160
ConcreteConcrete teamJun-2017475176299IIBEBO-ST140 = 70, IIBEBO-ST160 = 10, IIBEBO-ST360 = 50, IIBEBO-ST400 = 20, IIBEBO-ST420 = 40, IIBEBO-ST440 = 100, IIBEBO-ST730 = 40, IIIAWBO-ST520 = 15, IIIAWBO-ST570 = 40, IIIAWBO-ST580 = 40, IIIAWBO-ST700 = 50
Jul-2017816168648IIBEBO-ST160 = 60, IIBEBO-ST190 = 70, IIBEBO-ST200 = 70, IIBEBO-ST480 = 18, IIBEBO-ST500 = 150, IIBEBO-ST520 = 8, IIBEBO-ST730 = 30, IIBEBO-W130 = 150, IIIAWBO-ST111 = 50, IIIAWBO-ST120 = 50, IIIAWBO-ST570 = 60, IIIAWBO-ST580 = 60, IIIAWBO-ST620 = 40
Aug-2017833184649IIBEBO-ST250 = 18, IIBEBO-ST270 = 113, IIBEBO-ST520 = 33, IIBEBO-ST530 = 50, IIBEBO-ST540 = 50, IIBEBO-ST570 = 10, IIBEBO-ST580 = 30, IIBEBO-ST720 = 70, IIBEBO-W140 = 210, IIIAWBO-ST120 = 50, IIIAWBO-ST130 = 50, IIIAWBO-ST140 = 100, IIIAWBO-ST170 = 30, IIIBWBO-ST220 = 20
Sep-20171162168994IIBEBO-ST270 = 88, IIBEBO-ST330 = 50, IIBEBO-ST340 = 40, IIBEBO-ST390 = 30, IIBEBO-W140 = 10, IIBEBO-W150 = 190, IIIAWBO-ST150 = 27, IIIAWBO-ST160 = 113, IIIAWBO-ST170 = 40, IIIBWBO-ST220 = 30, IIIBWBO-ST240 = 50, IIIBWBO-ST260 = 50, IIIBWBO-ST270 = 45, IIIBWBO-ST28 = 60, IIIBWBO-ST300 = 50, IIIBWBO-ST330 = 30, IIIBWBO-ST370 = 60, IIIBWBO-ST750 = 150, IIIBWBO-W101 = 20, IIIBWBO-W110 = 30
Oct-201716211761445IIBEBO-W150 = 30, IIDEBO-ST190 = 50, IIDEBO-ST200 = 50, IIDEBO-ST210 = 20, IIIAWBO-ST160 = 108, IIIAWBO-ST171 = 50, IIIAWBO-ST181 = 100, IIIAWBO-ST211 = 40, IIIBWBO-ST211 = 70, IIIBWBO-ST250 = 70, IIIBWBO-ST270 = 105, IIIBWBO-ST28 = 140, IIIBWBO-ST280 = 40, IIIBWBO-ST320 = 70, IIIBWBO-ST330 = 40, IIIBWBO-ST340 = 18, IIIBWBO-ST350 = 120, IIIBWBO-ST360 = 10, IIIBWBO-ST370 = 20, IIIBWBO-ST400 = 150, IIIBWBO-ST430 = 50, IIIBWBO-W101 = 80, IIIBWBO-W110 = 190
Nov-2017854176678IIDEBO-ST210 = 30, IIDEBO-ST220 = 50, IIDEBO-ST230 = 18, IIDEBO-ST240 = 15, IIDEBO-ST340 = 70, IIIBWBO-ST100 = 135, IIIBWBO-ST280 = 30, IIIBWBO-ST310 = 70, IIIBWBO-ST350 = 80, IIIBWBO-ST380 = 18, IIIBWBO-ST390 = 8, IIIBWBO-ST410 = 70, IIIBWBO-ST430 = 30, IIIBWBO-ST480 = 160, IIIBWBO-W111 = 70
Dec-2017783168615IIDEBO-ST240 = 135, IIDEBO-ST330 = 60, IIIBWBO-ST100 = 15, IIIBWBO-ST390 = 193, IIIBWBO-ST440 = 50, IIIBWBO-ST450 = 80, IIIBWBO-ST510 = 30, IIIBWBO-ST520 = 70, IIIBWBO-ST560 = 120, IIIBWBO-ST610 = 23, IIIBWBO-ST690 = 8
Jan-2018650184466IIDEBO-ST250 = 60, IIDEBO-ST260 = 50, IIDEBO-ST290 = 30, IIDEBO-ST330 = 90, IIIBWBO-ST490 = 50, IIIBWBO-ST500 = 20, IIIBWBO-ST610 = 178, IIIBWBO-ST690 = 143, IIIBWBO-ST700 = 30
Feb-201825016090IIIBWBO-ST120 = 90, IIIBWBO-ST500 = 10, IIIBWBO-ST550 = 30, IIIBWBO-ST700 = 120
Apr-201821016842IVEBM-W150 = 100, IVEBM-W160 = 50, IVEBM-W170 = 60
May-201822018436IVEBM-W180 = 150, IVEBM-W190 = 50, IVEBM-W200 = 20
Jun-201821016842IVEBM-W200 = 80, IVEBM-W210 = 100, IVEBM-W220 = 30
DemoDemo TeamJun-2017290176114IBR-GC100 = 150, IIBR-GC140 = 20, IIIBWBO-GC100 = 80, IIICWBO-ST100 = 40
Jul-2017340168172IIBR-GC100 = 80, IIBR-GC170 = 100, IICR-GC100 = 20, IICR-GC170 = 20, IIIBWBO-GC100 = 20, IIICWBO-ST220 = 100
Aug-2017373184189IIDEBO-ST180 = 40, IIDEBO-ST300 = 20, IIIBWBO-ST180 = 20, IIIBWBO-ST190 = 80, IIIBWBO-ST640 = 50, IIIBWBO-ST650 = 80, IIIBWBO-ST660 = 50, IIIBWBO-ST670 = 33
Sep-2017457168289IIDEBO-ST300 = 80, IIDEBO-ST320 = 120, IIIBR-GC100 = 20, IIIBR-GC210 = 20, IIIBR-GC250 = 20, IIIBWBO-ST171 = 20, IIIBWBO-ST631 = 10, IIIBWBO-ST670 = 17, IIIBWBO-ST680 = 150
DrainageDrainage teamJun-2017754176578IBWBM-RW111 = 25, IIBEBO-SP100 = 150, IIBEBO-SP120 = 20, IIBEBO-SP160 = 200, IIBR-SP130 = 100, IIBR-SP210 = 30, IIBR-SP240 = 100, IIIBWBO-SP110 = 99, IIIBWBO-SP120 = 30
Jul-2017680168512IIBEBO-SP100 = 50, IIBEBO-SP130 = 160, IIBEBO-SP140 = 80, IIBR-SP100 = 50, IIBR-SP150 = 60, IICR-SP100 = 50, IICR-SP120 = 60, IIIBWBO-SP120 = 170
Aug-2017730184546IIBR-SP100 = 50, IIBR-SP150 = 40, IICR-SP120 = 40, IIIBWBO-SP130 = 200, IIIBWBO-SP140 = 200, IIIBWBO-SP150 = 200
Sep-2017380168212IIIBR-SP100 = 100, IIIBR-SP150 = 80, IIIBWBO-SP160 = 200
Dec-2017300168132IIIBR-SP130 = 100, IIIBR-SP160 = 100, IIICR-SP100 = 100
Apr-201826016892IVEBM-SP100 = 130, IVWBM-SP100 = 130
EmbankmentEmbankmentAug-2017575184391IIBR-EW100 = 220, IIBR-EW140 = 200, IIIBWBO-EW110 = 75, IIIBWBO-EW130 = 80
Jun-2017453176277IBR-EW100 = 220, IIBEBO-EW100 = 150, IIBR-EW130 = 3, IIBR-EW150 = 30, IIBR-EW210 = 30, IIIAWBO-ST24 = 20
Sep-201724516877IIIBWBO-EW101 = 45, IIIBWBO-EW102 = 80, IIIBWBO-EW130 = 120
Oct-2017463176287IIDEBO-RW150 = 143, IIIBR-EW100 = 50, IIIBR-EW150 = 50, IIIBWBO-EW102 = 90, IIIBWBO-EW103 = 130
PilePile teamJun-20171801764IIBEBO-ST2 = 30, IIBEBO-W100 = 150
Jul-201720016832IIBEBO-W110 = 150, IIBEBO-W120 = 50
Sep-201725016882IIIBWBO-ST2 = 30, IIIBWBO-ST26 = 100, IIIBWBO-W100 = 120
Oct-201722017644IIIBWBO-W100 = 30, IIIBWBO-W120 = 150, IIIBWBO-W130 = 40
BaseRoad base teamJun-201712921761116IBR-RW110 = 165, IIAR-RW110 = 20, IIBR-RW130 = 80, IIBR-RW190 = 30, IIBR-RW220 = 50, IIBR-RW310 = 30, IIBR-RW320 = 30, IIBR120 = 10, IICR-SP130 = 107, IICR100 = 150, IICR120 = 140, IIIAR100 = 30, IIIBR100 = 150, IIIBR110 = 150, IIICR100 = 150
Jul-2017688168520IBR-RW110 = 55, IIBR-RW170 = 80, IIBR-RW190 = 50, IIBR-RW220 = 30, IIBR-RW250 = 80, IICR-RW110 = 80, IICR-SP130 = 93, IICR100 = 10, IICR120 = 60, IIIBR100 = 50, IIIBR110 = 50, IIICR100 = 50
Aug-2017395184211IIBEBO-RW120 = 80, IIBR-RW110 = 5, IIBR-RW160 = 30, IICR-RW140 = 80, IIIAR120 = 200
Sep-2017495168327IIBEBM-GC110 = 20, IIBEBO-RW120 = 140, IIBR-RW110 = 15, IIBR-RW160 = 190, IIBR-RW280 = 50, IIBR-RW290 = 10, IIIAR110 = 60, IIIBR-RW190 = 10
Oct-2017996176820IIBEBM-GC110 = 10, IIBR-RW280 = 50, IIBR-RW290 = 140, IIDEBO-RW150 = 143, IIIBR-RW110 = 80, IIIBR-RW190 = 70, IIIBR-RW210 = 80, IIIBWBO-RW140 = 100, IIICR130 = 83, IIICR170 = 40, IIICR180 = 200
Nov-2017464176288IIDEBO-RW150 = 78, IIIBR-RW130 = 80, IIIBR-RW150 = 30, IIICR130 = 117, IIICR170 = 160
Dec-2017660168492IIIBR-RW150 = 50, IIIBR-RW230 = 30, IIIBWBM-GC110 = 30, IIICR110 = 150, IIICR140 = 200, IIICR200 = 200
Jan-2018777184593IIIBR-GC380 = 60, IIIBR-RW170 = 80, IIIBR-RW230 = 50, IIICR-RW110 = 80, IIICR110 = 50, IIICR120 = 107, IIICR160 = 150, IIICR190 = 200
Feb-2018317160157IIIBR-GC380 = 40, IIICR-RW130 = 80, IIICR120 = 93, IIICR150 = 53, IIICR160 = 50
SlagterSlagterOct-2017283176107IIBR-GC160 = 80, IIDEBO-RW150 = 143, IIIBR-GC120 = 20, IIIBR-GC290 = 20, IIIBR-GC320 = 20
StabilizationStabilization teamJun-2017681176505IBEBM-RW111 = 25, IBEBM-RW320 = 45, IBR-RW100 = 120, IIBEBO-RW112 = 110, IIBEBO-RW140 = 160, IIBEBO-RW160 = 60, IIBEBO-RW180 = 48, IIBR-RW120 = 20, IIBR-RW180 = 20, IIBR-RW200 = 20, IICR-SP130 = 53
Jul-2017322168154IIBEBO-RW110 = 70, IIBEBO-RW111 = 55, IIBEBO-RW130 = 90, IIBR-RW150 = 20, IIBR-RW240 = 20, IICR-RW100 = 20, IICR-SP130 = 47
Aug-2017480184296IIBEBO-RW110 = 150, IIBEBO-RW130 = 60, IIBEBO-RW150 = 70, IIBR-RW100 = 60, IIBR-RW140 = 120, IICR-RW150 = 20
Sep-2017280168112IIIBR-RW180 = 20, IIIBWBO-RW100 = 120, IIIBWBO-RW110 = 120, IIIBWBO-RW120 = 20
Oct-2017663176487IIDEBO-RW150 = 143, IIIBR-RW100 = 20, IIIBR-RW200 = 20, IIIBWBO-RW100 = 80, IIIBWBO-RW110 = 80, IIIBWBO-RW120 = 180, IIIBWBO-RW150 = 100, IIIBWBO-RW160 = 40
Nov-20171781762IIDEBO-RW150 = 78, IIIBR-RW120 = 20, IIIBR-RW140 = 20, IIIBWBO-RW160 = 60
Jul-2018300176124IVWBM-RW140 = 40, IVWBM-RW150 = 90, IVWBM-RW260 = 50, IVWBM-RW270 = 40, IVWBM-RW280 = 80
MOTTraffic Control TeamJun-2017290176114IICR-TC1000 = 10, IICR-TC130 = 10, IICR-TC160 = 10, IICR-TC170 = 100, IICR-TC180 = 10, IICR-TC200 = 10, IICR-TC210 = 10, IIIAWBO-TC100 = 10, IIIAWBO-TC110 = 10, IIIAWBO-TC120 = 10, IIIAWBO-TC130 = 30, IIIBWBO-TC110 = 30, IIIBWBO-TC120 = 40
Jul-2017275168107IBEBM-TC220 = 173, IIBEBO-ST480 = 12, IIBR-TC160 = 30, IIBR-TC170 = 10, IIBR-TC270 = 10, IICR-TC1020 = 10, IICR-TC120 = 10, IIIBR-TC120 = 10, IIIBR-TC130 = 10
Aug-201726918485IBEBM-TC220 = 27, IIAR-TC120 = 120, IIAR-TC130 = 90, IIBEBO-ST250 = 12, IICR-TC150 = 10, IICR-TC190 = 10
Sep-201726316895IIAR-TC120 = 80, IIAR-TC130 = 110, IIIAWBO-ST150 = 13, IIIBR-TC160 = 10, IIIBR-TC170 = 10, IIIBR-TC220 = 10, IIIBR-TC230 = 10, IIIBR-TC250 = 10, IIIBR-TC260 = 10
Nov-201719417618IIDEBO-ST230 = 12, IIIBR-TC270 = 10, IIIBR-TC280 = 10, IIIBR140 = 150, IIIBWBO-ST380 = 12
US&SUS & SJun-2017757176581IBR-IHM300 = 25, IIBR-EC10 = 30, IIBR-EHM360 = 10, IIBR-IB10 = 30, IIBR-IDS30 = 42, IIBR-IHM310 = 60, IIBR-IHM320 = 60, IIBR-SM380 = 130, IIIBR-EC20 = 60, IIIBR-IHM330 = 10, TF-CO-001 = 150, TF-CO-003 = 50, TF-CO-008 = 100
Oct-201712901761114IIBR-SM470 = 30, IIBR-SM480 = 30, IIBR-SM490 = 160, IIIBR-ET40 = 40, IIIBR-RES130 = 180, IIIBR-SM520 = 70, IIIBR-SM530 = 150, IVR-ET50 = 180, IVR-SM660 = 10, TF-CO-006 = 50, TF-CO-009 = 170, TF-CO-025 = 70, TF-CO-029 = 150
Sep-2017945168777IIBR-SM430 = 30, IIBR-SM440 = 54, IIBR-SM450 = 57, IIBR-SM460 = 54, IIIBR-ET40 = 120, IIIBR-IDS40 = 60, IIIBR-SM510 = 150, IIIBR-SM520 = 20, TF-CO-004 = 100, TF-CO-006 = 100, TF-CO-023 = 50, TF-CO-025 = 150
Jul-2017850168682IIBEBO-IE20 = 100, IIBR-CP10 = 60, IIBR-EHM360 = 170, IIBR-EHM370 = 30, IIBR-IB10 = 20, IIBR-IB180 = 150, IIBR-SM380 = 10, IIBR-SM390 = 80, IIBR-SM400 = 80, IIBR-SM410 = 30, IIIBR-IHM330 = 50, TF-CO-001 = 70
Aug-2017510184326IIBR-CP10 = 40, IIBR-EHM370 = 90, IIBR-IB180 = 50, IIBR-SM410 = 50, IIBR-SM420 = 140, IIBR-SM430 = 40, TF-CO-004 = 100
Dec-20171020168852IIIBR-SM540 = 30, IIIBR-SM550 = 70, IIIBR-SM560 = 80, IVR-SM670 = 20, IVR-SM680 = 160, TF-CO-013 = 60, TF-CO-014 = 150, TF-CO-015 = 150, TF-CO-018 = 150, TF-CO-019 = 150
Nov-2017970176794IIBR-SM490 = 40, IIBR-SM500 = 100, IIIBR-SM530 = 50, IIIBR-SM540 = 170, IVR-ET60 = 140, IVR-SM660 = 70, IVR-SM670 = 140, TF-CO-009 = 50, TF-CO-012 = 100, TF-CO-013 = 40, TF-CO-029 = 70
Mar-20181040176864IIIBR-SM580 = 70, IIIBR-SM590 = 120, IIIBR-SM600 = 30, IVEBO-SS100 = 100, IVR-EC30 = 60, IVR-IPM70 = 200, IVR-IPM80 = 20, IVR-RES140 = 60, IVWBO-SS100 = 100, TF-CO-016 = 60, TF-CO-017 = 60, TF-CO-024 = 160
Apr-201813401681172IIIBR-SM600 = 90, IIIBR-SM610 = 120, IVEBO-SS100 = 100, IVR-IPM100 = 40, IVR-IPM80 = 180, IVR-IPM90 = 200, IVWBO-SS100 = 100, TF-CO-024 = 60, TF-CO-026 = 150, TF-CO-027 = 150, TF-CO-028 = 150
Jan-2018920184736IIIBR-CP10 = 90, IIIBR-CP170 = 50, IIIBR-SM560 = 30, IIIBR-SM570 = 140, IIIC-AP170 = 80, IIIC-CP10 = 80, IVR-SM690 = 180, TF-CO-010 = 30, TF-CO-018 = 70, TF-CO-019 = 70, TF-CO-020 = 100
May-2018830184646IIIBR-IBM110 = 40, IIIBR-SM620 = 120, IIIBR-SM630 = 110, IVR-IPM100 = 160, TF-CO-026 = 70, TF-CO-027 = 100, TF-CO-028 = 100, TF-CO-030 = 130
Feb-20181080160920IIIBR-CP10 = 10, IIIBR-SM570 = 60, IIIBR-SM580 = 130, IIIC-AP170 = 120, IIIC-CP10 = 120, IVR-SM690 = 20, IVR-SM700 = 160, TF-CO-010 = 40, TF-CO-016 = 160, TF-CO-017 = 160, TF-CO-021 = 50, TF-CO-022 = 50
Jun-2018400168232IIIBR-SM630 = 90, IIIBR-SM640 = 90, IIIBR-SM650 = 20, TF-CO-030 = 90, TF-CO-031 = 110
Jul-2018340176164IIIBR-SM650 = 180, TF-CO-031 = 110, TF-CO-032 = 50

Lists project milestones, grouped by their WBS sequence and name, showing only those with negative float.

Highlighted in red are milestones with negative total or free float. This can indicate that a milestone is behind a requirement or constraining downstream work, but the cause must be established from its dates, constraints, logic, and project context.

Recommended actions:

  • Check for conflicting constraints or deadlines on these milestones.
  • Validate predecessor/successor links to ensure logic is correct.
  • Adjust sequencing or resource assignments as needed, then re‐run the schedule to confirm the float values return to zero or positive.

WBS Seq: NameMilestone IDMilestone NameTypeStatusTarget StartTarget FinishActual StartActual FinishTotal FloatFree Float
0: GeneralPH MS - Start Phase IV ConstructionStartNot Started16-Mar-1816-Mar-18-110
PH MS - Substantial CompletionFinishNot Started25-Aug-1825-Aug-18-512
4: Maintenance of TrafficPH MS - Project CompletionFinishNot Started05-Sep-1805-Sep-18-170

Lists project milestones, grouped by their WBS sequence and name.

Highlighted in red are milestones with negative total or free float. This can indicate that a milestone is behind a requirement or constraining downstream work, but the cause must be established from its dates, constraints, logic, and project context.

Recommended actions:

  • Check for conflicting constraints or deadlines on these milestones.
  • Validate predecessor/successor links to ensure logic is correct.
  • Adjust sequencing or resource assignments as needed, then re‐run the schedule to confirm the float values return to zero or positive.

WBS Seq: NameMilestone IDMilestone NameTypeStatusTarget StartTarget FinishActual StartActual FinishTotal FloatFree Float
0: GeneralPH MS - NTPStartCompleted14-Nov-1514-Nov-1519-Aug-1519-Aug-1500
PH MS - Start Phase IA ConstructionStartCompleted14-Nov-1514-Nov-1520-Sep-1520-Sep-1500
PH MS - Start Phase IB ConstructionStartCompleted20-Nov-1520-Nov-1520-Nov-1520-Nov-1500
PH MS - NTP2 - Start Construction (35 days from NTP 1= Contract date )StartCompleted16-Dec-1516-Dec-1520-Sep-1520-Sep-1500
PH MS - Start Phase IIA ConstructionStartCompleted17-Oct-1617-Oct-1619-Sep-1619-Sep-1600
PH MS - Start Phase IIB ConstructionStartCompleted04-Jan-1704-Jan-1704-Oct-1604-Oct-1600
PH MS - Start Phase IIC ConstructionStartNot Started12-Jun-1712-Jun-17400
PH MS - Start Phase IIIA ConstructionStartNot Started12-Jun-1712-Jun-17200
PH MS - Start Phase IID ConstructionStartNot Started24-Aug-1724-Aug-17210
PH MS - Start Phase IIIB ConstructionStartNot Started14-Sep-1714-Sep-1710
PH MS - Start Phase IIIC ConstructionStartNot Started11-Dec-1711-Dec-1710
PH MS - Start Phase IV ConstructionStartNot Started16-Mar-1816-Mar-18-110
PH MS - Substantial CompletionFinishNot Started25-Aug-1825-Aug-18-512
4: Maintenance of TrafficPH MS - Project CompletionFinishNot Started05-Sep-1805-Sep-18-170

Performance % methodActivity Percent Complete26 displayed WBS elementsETC methodRemaining Cost for Activity26 displayed WBS elementsInterpretation: These are P6 calculation settings, not calculated EV or ETC results. Manual percentages and performance factors are shown only when the selected method uses them. This report groups remaining activity work by open WBS and shows the earliest and latest target and actual dates for each element. Use it to spot unfinished scope and compare planned dates with recorded progress. Remaining work follows your duration-unit preference.

WBS Seq: NameRemaining WorkTarget StartTarget FinishActual StartActual Finish
0: General3089 days19-Aug-1505-Sep-1819-Aug-1509-Jun-17
1: SPS &CPS Wall113 days12-Jun-1716-Nov-17
1: Retaining Walls145 days18-Apr-1605-Jul-1811-May-1625-Apr-17
1: MSE Walls83 days17-May-1626-Oct-1706-Jun-1627-Jul-16
1: Exc Ponds18 days14-Dec-1509-Oct-1726-Oct-1516-Jan-17
1: Embankment & Exc Road246 days14-Dec-1506-Feb-1805-Oct-1519-May-17
1: Misc Demo96 days27-Jan-1628-Mar-1826-Oct-1501-May-17
1: Barrier Wall (MOT)261 days29-Oct-1521-Mar-1821-Oct-1522-May-17
1: Temporary signs & Barricades1 days16-Nov-1512-Jun-1720-Sep-1503-Oct-16
4: Maintenance of Traffic1 days16-Dec-1505-Sep-1808-Oct-1509-Sep-16
7: Site Preparation & Access9 days05-Nov-1520-Jun-1705-Nov-1522-Aug-16
8: Drainage449 days17-Feb-1618-Apr-1806-Jan-1608-Jun-17
10: Walls94 days05-Apr-1601-Feb-1816-Feb-1604-May-17
10: Demo (Bridge)131 days14-Dec-1516-Oct-1722-Nov-1511-May-17
10: Foundations27 days14-Dec-1523-Oct-1720-Nov-1502-Jun-17
11: (MOT) Structural Pavement1 days17-Apr-1713-Jun-1729-Mar-1706-Apr-17
13: (MOT) Pavement Markings1 days13-Jan-1620-Jun-1727-Sep-1501-Dec-15
14: Toll Facility564 days31-Mar-1723-Aug-1820-Mar-1731-Mar-17
101: Substructure93 days08-Mar-1630-Oct-1729-Jan-1617-Mar-17
101: Walls (Abutm & Wing)228 days05-May-1608-Dec-1718-Apr-1607-Jun-17
201: Superstructure287 days23-May-1616-Feb-1823-May-1630-May-17
301: Approach Slabs66 days06-Jul-1605-Mar-1813-Jul-1610-May-17
400: Beachline Update#20 DD June 11 TD June 15175 days12-Jun-1716-Feb-18
401: Imbeded Facilities (Electrical, Communications)13 days20-Jan-1706-Mar-1826-Jan-1718-May-17
501: Railing walls34 days01-Aug-1609-Mar-1804-Aug-1620-May-17
601: Finishes & Misc34 days04-Aug-1615-Mar-1803-Aug-1609-Jun-17

Successful Tests (no errors, changes, or issues)

  • Activities with Future Actual Dates
  • Activities with Missing Predecessors ImprovedNow uses remaining work and valid network boundary rules.
  • Activities with Missing Successors ImprovedNow uses remaining work and valid network boundary rules.
  • Activity Constraints ImprovedNow shows primary and secondary P6 types without a generic satisfaction guess.

Back Project Costs

The figures in this report should not be relied upon, excercise caution and double-check the values. This is merely a preview of a work-in-progress feature.
This table represents monthly project costs.

MonthActualActual CumulRemaining EarlyRemaining Early CumulRemaining LateRemaining Late Cumul
Aug-2015$5,537,599.61$5,537,599.610000
Sep-2015$2,445,696.60$7,983,296.210000
Oct-2015$3,171,096.91$11,154,393.120000
Nov-2015$1,372,651.15$12,527,044.270000
Dec-2015$1,093,149.68$13,620,193.950000
Jan-2016$666,775.56$14,286,969.510000
Feb-2016$1,000,323.64$15,287,293.150000
Mar-2016$662,043.51$15,949,336.650000
Apr-2016$689,435.13$16,638,771.780000
May-2016$1,853,885.53$18,492,657.310000
Jun-2016$2,101,471.48$20,594,128.790000
Jul-2016$2,719,063.08$23,313,191.870000
Aug-2016$1,619,326.51$24,932,518.390000
Sep-2016$1,429,111.36$26,361,629.750000
Oct-2016$1,245,161.83$27,606,791.590000
Nov-2016$1,131,474.20$28,738,265.790000
Dec-2016$3,630,160.50$32,368,426.280000
Jan-2017$2,489,504.53$34,857,930.810000
Feb-2017$2,351,203.14$37,209,133.950000
Mar-2017$3,060,488.40$40,269,622.360000
Apr-2017$2,079,382.07$42,349,004.420000
May-2017$2,150,416.80$44,499,421.2200$274,448.75$274,448.75
Jun-2017$807,088.73$45,306,509.95$6,314,001.15$6,314,001.15$1,492,428.50$1,766,877.26
Jul-201700$6,391,443.98$12,705,445.13$3,555,290.11$5,322,167.37
Aug-201700$4,410,405.59$17,115,850.72$4,708,404.90$10,030,572.27
Sep-201700$4,441,268.62$21,557,119.34$6,203,475.49$16,234,047.76
Oct-201700$6,303,210.34$27,860,329.68$3,430,737.24$19,664,785.00
Nov-201700$2,884,771.37$30,745,101.05$2,365,848.94$22,030,633.94
Dec-201700$3,187,722.49$33,932,823.54$4,348,599.06$26,379,232.99
Jan-201800$3,175,803.69$37,108,627.23$3,105,211.28$29,484,444.27
Feb-201800$2,006,503.17$39,115,130.40$7,032,683.90$36,517,128.17
Mar-201800$1,873,781.02$40,988,911.41$1,038,265.12$37,555,393.29
Apr-201800$1,505,955.76$42,494,867.17$1,000,871.36$38,556,264.66
May-201800$1,015,198.89$43,510,066.06$1,237,041.24$39,793,305.89
Jun-201800$776,140.79$44,286,206.85$2,046,014.28$41,839,320.17
Jul-201800$684,180.17$44,970,387.03$3,816,513.83$45,655,834.00
Aug-201800$2,414,153.45$47,384,540.48$1,801,005.32$47,456,839.33
Sep-201800$72,298.85$47,456,839.330$47,456,839.33

Back Charts

Download

The figures in this report should not be relied upon, excercise caution and double-check the values. This is merely a preview of a work-in-progress feature.
This chart represents monthly project costs

Report chart